Pre-Inspection
|
1/21/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/4/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
2/4/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/5/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/6/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/10/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
2/10/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/11/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/12/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/13/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/14/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/18/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
2/18/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/19/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/20/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/21/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/25/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
2/25/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/26/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/27/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
2/28/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
3/3/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/6/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/9/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
3/10/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/12/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
3/12/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/16/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/17/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
3/17/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
3/17/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
3/19/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
3/20/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/23/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
3/23/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/24/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/25/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
3/25/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
3/26/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
3/26/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Piling/Pier/Caisson
|
3/27/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
3/31/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/2/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Piling/Pier/Caisson
|
4/2/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
4/7/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/8/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/13/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/14/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
4/14/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
4/22/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/24/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/27/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/28/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/29/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
4/29/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
4/29/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
4/30/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/1/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/5/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Footing/Foundation/Slab
|
5/5/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Steel/Welding
|
5/6/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/7/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
5/7/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/8/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/11/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/13/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
5/13/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/14/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/15/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/18/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/19/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
5/19/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/20/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/26/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
5/26/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/28/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
5/29/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/2/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
6/2/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/3/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/5/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/8/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
6/9/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/10/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/15/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/16/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Grading Pre-Inspection
|
6/16/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
6/16/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
6/17/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/22/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
6/22/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
6/23/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
6/24/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/25/2020
|
Conditional Approval
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/29/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
6/30/2020
|
Approved
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
6/30/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
7/7/2020
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Piling/Pier/Caisson
|
7/15/2020
|
Partial Approval
|
DANIEL MC AULIFFE
|
|
Excavation/Setback/Form/Re-Bar
|
3/16/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Pre-Inspection
|
8/2/2021
|
Partial Inspection
|
DANIEL MC AULIFFE
|
|
Deputy Grading
|
9/9/2021
|
Approved
|
DANIEL MC AULIFFE
|
|
Final
|
10/28/2021
|
Permit Finaled
|
DANIEL MC AULIFFE
|