640 S SANTA FE AVE 90021
Certificate Information: 640 S SANTA FE AVE 90021
- Application / Permit
- 19020-10000-02000
- Plan Check / Job No.
- B19LA15229
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Early start temporary shoring support for (N) 4-story commerical building
- Permit Issued
- Issued on 10/18/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | TU HUA |
| Corrections Issued | 8/8/2019 | TU HUA |
| Quality Review Completed | 8/20/2019 | MINYE PAK |
| Building Plans Picked Up | 8/22/2019 | APPLICANT |
| Applicant returned to address corrections | 9/4/2019 | TU HUA |
| Applicant returned to address corrections | 10/9/2019 | TU HUA |
| Plan Check Approved | 10/18/2019 | CATHERINE CHEN |
| Issued | 10/18/2019 | LADBS |
| Permit Finaled | 6/23/2021 | RAFAEL ESPINOZA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2019 | ELAINE LEI |
| Encroachment in public way | Cleared | 9/11/2019 | ELAINE LEI |
| Building over 3-story or 36-ft | Cleared | 9/20/2019 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 9/20/2019 | CALOSHA APPROVED |
| Low Impact Development | Cleared | 9/20/2019 | MARTIN FRAGOSO |
| Green Code | Cleared | 9/24/2019 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 9/24/2019 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 9/24/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/24/2019 | ERIK BEASLEY |
| Site Plan review | Cleared | 9/24/2019 | DIANA JIMENEZ |
| ZI | Cleared | 9/24/2019 | DIANA JIMENEZ |
| Driveway location | Cleared | 10/1/2019 | COLLINS ALLAN |
| Fire Marshall Fire Life Safety | Cleared | 10/1/2019 | ANDREW KO |
| Internal circulation | Cleared | 10/1/2019 | COLLINS ALLAN |
| Miscellaneous | Cleared | 10/10/2019 | DIANA JIMENEZ |
| Work Adjacent to Public Way | Cleared | 10/17/2019 | BOK GOH |
Contact Information
| Contractor | Pankow Charles Builders Ltd; Lic. No.: 688972-B | 199 S LOS ROBLES AVE #300 PASADENA, CA 91101 |
| Engineer | Ip,, Vincent Ping-Kuen; Lic. No.: GE2522 | 16 CITY STROLL IRVINE, CA 92620 |
| Engineer | Woodley,, George Allen; Lic. No.: C54744 | 12645 CLARK STREET SANTA FE SPRINGS, CA 90670 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/22/2019 | Approved | ERNESTO CORRAL |
| Deputy Grading | 10/23/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 10/23/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 10/24/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 10/25/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 10/28/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 10/29/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 10/30/2019 | Partial Approval | RONALD PACHECO |
| Deputy Steel/Welding | 10/31/2019 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 11/1/2019 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 11/18/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 11/19/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 11/20/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 11/21/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Steel/Welding | 11/22/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/2/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/3/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/4/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/5/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/6/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/11/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/12/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/13/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/18/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/19/2019 | Conditional Approval | JEFFREY FULTON |
| Deputy Grading | 12/20/2019 | Conditional Approval | RONALD PACHECO |
| Deputy Grading | 12/23/2019 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 12/24/2019 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 12/30/2019 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 12/31/2019 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 12/31/2019 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/2/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/6/2020 | Conditional Approval | ERNESTO CORRAL |
| Excavation/Setback/Form/Re-Bar | 1/6/2020 | Partial Inspection | ERNESTO CORRAL |
| Deputy Grading | 1/7/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/8/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/9/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/10/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/15/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 1/15/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/16/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/17/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 1/17/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/24/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/27/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/28/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 1/28/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/29/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 1/29/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 1/30/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 2/3/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 2/27/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 2/28/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 3/2/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/2/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/3/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/3/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/4/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Shotcrete | 3/4/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 3/5/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/5/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/6/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/6/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/9/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/9/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/10/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/10/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/11/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/11/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/12/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/12/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Shotcrete | 3/12/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/13/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/13/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 3/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 3/19/2020 | Conditional Approval | DANIEL MC AULIFFE |
| Deputy Shotcrete | 3/19/2020 | Approved | DANIEL MC AULIFFE |
| Deputy Reinf. Concrete | 3/20/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Shotcrete | 3/20/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 3/23/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/23/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Shotcrete | 3/23/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 3/24/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/24/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/25/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 3/25/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/26/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 3/27/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 4/1/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 4/1/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 4/2/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 4/2/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 4/3/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 4/3/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 4/6/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/6/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/7/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 4/7/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Drilled-In Anchors | 4/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 4/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 4/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 4/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 4/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/29/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 4/29/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 4/30/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/1/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/5/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/5/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/6/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/6/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 5/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 5/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 5/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 5/12/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/12/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/12/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 5/13/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/13/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Shotcrete | 5/13/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 5/29/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 6/1/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 6/2/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 6/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/15/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/18/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/19/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/25/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 6/26/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/1/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/2/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/6/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/10/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 7/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/29/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/30/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 7/31/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/3/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 8/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 8/5/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/5/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 8/6/2020 | Conditional Approval | NICK DANERI |
| Deputy Steel/Welding | 8/6/2020 | Conditional Approval | NICK DANERI |
| Deputy Reinf. Concrete | 8/7/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/7/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 8/7/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 8/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/12/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/13/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/14/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/14/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/18/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/19/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 8/25/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/25/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 8/26/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/26/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 8/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 8/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 8/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 8/31/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/1/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/2/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/3/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/10/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/10/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/14/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/14/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/15/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/15/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 9/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/18/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/18/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/25/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/25/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Fireproofing | 9/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/28/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/29/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 9/30/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/1/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 10/2/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/2/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/5/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/6/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 10/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/7/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 10/14/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 10/15/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/19/2020 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 10/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/23/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/27/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/29/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/30/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 11/13/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/16/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/17/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 11/20/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/24/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 11/25/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 11/30/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/2/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/3/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 12/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/4/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/8/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/9/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/10/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/11/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 12/21/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 12/22/2020 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 1/20/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 1/22/2021 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 2/11/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 2/12/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 3/2/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 3/2/2021 | Conditional Approval | ERNESTO CORRAL |
| Deputy Steel/Welding | 3/3/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 3/4/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 4/15/2021 | Conditional Approval | RONALD PACHECO |
| Deputy Steel/Welding | 4/16/2021 | Conditional Approval | LANNY MERRICK |
| Final | 6/23/2021 | Permit Finaled | RAFAEL ESPINOZA |