3633 N RODERICK ROAD 90065
Certificate Information: 3633 N RODERICK ROAD 90065
- Application / Permit
- 19020-10000-01489
- Plan Check / Job No.
- B19LA11163
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- CONSTRUCT FREE-STANDING GARDEN WALLS AND RETAINING WALLS ON PILES FOR COLUMBARIUM WITH ASSCOIATED STAIRCASE AND PLANTER AREAS. (1 of 2)
- Permit Issued
- Issued on 10/23/2020
- Issuing Office
- Metro
- Current Status
- Issued on 10/23/2020
Permit Application Status History
| Submitted | 5/30/2019 | APPLICANT |
| Application Withdrawn | 5/30/2019 | APPLICANT |
| Re-Activate Applicaton | 5/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | VU NGUYEN |
| Corrections Issued | 7/11/2019 | VU NGUYEN |
| Disabled Access Plans Picked Up | 7/16/2019 | APPLICANT |
| Quality Review Completed | 7/22/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 10/16/2019 | VU NGUYEN |
| Plan Check Approved | 10/31/2019 | VU NGUYEN |
| Issued | 10/23/2020 | APPLICANT |
| Building Plans Picked Up | 5/18/2021 | APPLICANT |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 10/9/2019 | RICHARD REASER |
| ZA Case | Cleared | 10/9/2019 | RICHARD REASER |
| ZA Case | Cleared | 10/9/2019 | RICHARD REASER |
| ZI | Cleared | 10/9/2019 | RICHARD REASER |
| Grading Pre-Inspection | Cleared | 10/16/2019 | VU NGUYEN |
| DAS Clearance | Cleared | 10/18/2019 | SOMKIAT SUPANYACHOTSKUL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schulz,, Les Eric; Lic. No.: S2570 | 346 N LIMA SIERRA MADRE, CA 91024 |
| Geologist | Byer,, John W; Lic. No.: EG883 | 1649 PUEBLA DRIVE GLENDALE, CA 91207 |
Inspector Information
| JONATHAN HOM, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT HUGHES, (213) 482-7452 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 10/12/2021 | Partial Approval | ALEXANDER HELFER |
| Deputy Drilled-In Anchors | 11/15/2021 | Approved | ROBERT HUGHES |
| Deputy Reinf. Concrete | 11/15/2021 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 11/22/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 11/23/2021 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 12/15/2021 | Approved | ROBERT HUGHES |
| Deputy Reinf. Concrete | 1/25/2022 | Approved | ROBERT HUGHES |
| Deputy Reinf. Concrete | 2/7/2022 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 2/8/2022 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 2/11/2022 | Partial Approval | ROBERT HUGHES |
| Grading Pre-Inspection | 2/23/2022 | Partial Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 3/17/2022 | Conditional Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 4/15/2022 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 4/25/2022 | Conditional Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 5/12/2022 | Not Ready for Inspection | ROBERT HUGHES |
| Footing/Foundation/Slab | 5/27/2022 | Partial Approval | MATTHEW JENKINS |
| Deputy Reinf. Concrete | 6/22/2022 | No Access for Inspection | MATTHEW JENKINS |
| Piling/Pier/Caisson | 6/22/2022 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 7/15/2022 | Approved | ROBERT HUGHES |
| Deputy Reinf. Concrete | 7/18/2022 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 7/18/2022 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 7/21/2022 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 8/19/2022 | Partial Approval | ROBERT HUGHES |
| Reinforced Concrete Frame | 9/6/2022 | Partial Approval | ROBERT HUGHES |
| Reinforced Concrete Frame | 9/14/2022 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 9/16/2022 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 10/4/2022 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 10/26/2022 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 12/20/2022 | Partial Approval | ROBERT HUGHES |
| Deputy Drilled-In Anchors | 1/23/2023 | Conditional Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 1/26/2023 | Partial Approval | JONATHAN HOM |
| Deputy Reinf. Concrete | 2/13/2023 | Approved | KIRK LINKLATER |
| Reinforced Concrete Frame | 2/13/2023 | Conditional Approval | JONATHAN HOM |
| Footing/Foundation/Slab | 3/16/2023 | Approved | LANNY MERRICK |
| Deputy Reinf. Concrete | 3/20/2023 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 4/21/2023 | Conditional Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 5/15/2023 | Approved | ROBERT HUGHES |
| Deputy Shotcrete | 5/26/2023 | Approved | ROBERT HUGHES |
| Deputy Reinf. Concrete | 6/12/2023 | Approved | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 7/10/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 7/10/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 8/30/2023 | Approved | ROBERT HUGHES |
| Deputy Reinf. Concrete | 11/14/2023 | Approved | ROBERT HUGHES |