3633 N RODERICK ROAD 90065

Certificate Information: 3633 N RODERICK ROAD 90065

Application / Permit
19020-10000-01489
Plan Check / Job No.
B19LA11163
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Retaining Wall
Work Description
CONSTRUCT FREE-STANDING GARDEN WALLS AND RETAINING WALLS ON PILES FOR COLUMBARIUM WITH ASSCOIATED STAIRCASE AND PLANTER AREAS. (1 of 2)
Permit Issued
Issued on 10/23/2020
Issuing Office
Metro
Current Status
Issued on 10/23/2020

Permit Application Status History

Submitted 5/30/2019 APPLICANT
Application Withdrawn 5/30/2019 APPLICANT
Re-Activate Applicaton 5/30/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 VU NGUYEN
Corrections Issued 7/11/2019 VU NGUYEN
Disabled Access Plans Picked Up 7/16/2019 APPLICANT
Quality Review Completed 7/22/2019 JOSE RODRIGUEZ
Applicant returned to address corrections 10/16/2019 VU NGUYEN
Plan Check Approved 10/31/2019 VU NGUYEN
Issued 10/23/2020 APPLICANT
Building Plans Picked Up 5/18/2021 APPLICANT

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 10/9/2019 RICHARD REASER
ZA Case Cleared 10/9/2019 RICHARD REASER
ZA Case Cleared 10/9/2019 RICHARD REASER
ZI Cleared 10/9/2019 RICHARD REASER
Grading Pre-Inspection Cleared 10/16/2019 VU NGUYEN
DAS Clearance Cleared 10/18/2019 SOMKIAT SUPANYACHOTSKUL

Contact Information

Contractor Owner-Builder       ,
Engineer Schulz,, Les Eric; Lic. No.: S2570 346 N LIMA      SIERRA MADRE, CA 91024
Geologist Byer,, John W; Lic. No.: EG883 1649 PUEBLA DRIVE      GLENDALE, CA 91207

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/12/2021 Partial Approval ALEXANDER HELFER
Deputy Drilled-In Anchors 11/15/2021 Approved ROBERT HUGHES
Deputy Reinf. Concrete 11/15/2021 Approved ROBERT HUGHES
Footing/Foundation/Slab 11/22/2021 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 11/23/2021 Approved ROBERT HUGHES
Footing/Foundation/Slab 12/15/2021 Approved ROBERT HUGHES
Deputy Reinf. Concrete 1/25/2022 Approved ROBERT HUGHES
Deputy Reinf. Concrete 2/7/2022 Approved ROBERT HUGHES
Footing/Foundation/Slab 2/8/2022 Partial Approval ROBERT HUGHES
Footing/Foundation/Slab 2/11/2022 Partial Approval ROBERT HUGHES
Grading Pre-Inspection 2/23/2022 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 3/17/2022 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 3/17/2022 Partial Approval ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 4/15/2022 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 4/25/2022 Conditional Approval MATTHEW JENKINS
Footing/Foundation/Slab 5/12/2022 Not Ready for Inspection ROBERT HUGHES
Footing/Foundation/Slab 5/27/2022 Partial Approval MATTHEW JENKINS
Deputy Reinf. Concrete 6/22/2022 No Access for Inspection MATTHEW JENKINS
Piling/Pier/Caisson 6/22/2022 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 7/15/2022 Approved ROBERT HUGHES
Deputy Reinf. Concrete 7/18/2022 Approved ROBERT HUGHES
Footing/Foundation/Slab 7/18/2022 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 7/21/2022 Approved ROBERT HUGHES
Footing/Foundation/Slab 8/19/2022 Partial Approval ROBERT HUGHES
Reinforced Concrete Frame 9/6/2022 Partial Approval ROBERT HUGHES
Reinforced Concrete Frame 9/14/2022 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 9/16/2022 Approved ROBERT HUGHES
Footing/Foundation/Slab 10/4/2022 Partial Approval ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 10/12/2022 Partial Approval ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 10/26/2022 Partial Approval ROBERT HUGHES
Footing/Foundation/Slab 12/20/2022 Partial Approval ROBERT HUGHES
Deputy Drilled-In Anchors 1/23/2023 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 1/26/2023 Partial Approval JONATHAN HOM
Deputy Reinf. Concrete 2/13/2023 Approved KIRK LINKLATER
Reinforced Concrete Frame 2/13/2023 Conditional Approval JONATHAN HOM
Footing/Foundation/Slab 3/16/2023 Approved LANNY MERRICK
Deputy Reinf. Concrete 3/20/2023 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 4/21/2023 Conditional Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 4/25/2023 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 5/15/2023 Approved ROBERT HUGHES
Deputy Shotcrete 5/26/2023 Approved ROBERT HUGHES
Deputy Reinf. Concrete 6/12/2023 Approved ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 7/10/2023 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 7/10/2023 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 8/30/2023 Approved ROBERT HUGHES
Deputy Reinf. Concrete 11/14/2023 Approved ROBERT HUGHES