6001 W 96TH ST UNIT 87 90045

Certificate Information: 6001 W 96TH ST UNIT 87 90045

Application / Permit
19020-10000-01343
Plan Check / Job No.
B19LA10094
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
LAX GUIDEWAY 3GW3 FOR LAX AUTOMATED PEOPLE MOVER PROJECT.
Permit Issued
Issued on 2/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 DEAN RYAN REYES
Corrections Issued 6/14/2019 DEAN RYAN REYES
Quality Review Completed 6/14/2019 MINYE PAK
Building Plans Picked Up 6/17/2019 APPLICANT
Disabled Access Plans Picked Up 7/30/2019 APPLICANT
Applicant returned to address corrections 11/19/2019 DEAN RYAN REYES
Applicant returned to address corrections 12/2/2019 DEAN RYAN REYES
Applicant returned to address corrections 2/7/2020 DEAN RYAN REYES
Plan Check Approved 2/7/2020 DEAN RYAN REYES
Issued 2/10/2020 LADBS
CofO in Progress 10/7/2025 NICK LAROCCA
Permit Finaled 10/7/2025 NICK LAROCCA
CofO Issued 10/7/2025 NICK LAROCCA
Permit Finaled 10/7/2025 NICK LAROCCA

Permit Application Clearance Information

ZA Case Cleared 6/26/2019 SOPHIE GABEL-SCHEINBAU
Tract Map conditions Cleared 7/2/2019 DIANA JIMENEZ
Tract Map conditions Cleared 7/2/2019 DIANA JIMENEZ
Tract Map conditions Cleared 7/2/2019 DIANA JIMENEZ
Project Permit Cleared 7/3/2019 DEAN RYAN REYES
Address approval Cleared 7/15/2019 MARYAM AZARBAYJANI
Encroachment in public way Cleared 7/15/2019 MARYAM AZARBAYJANI
Eng Process Fee Ord 176,300 Cleared 7/15/2019 MARYAM AZARBAYJANI
Roof/Waste drainage to street Cleared 7/15/2019 MARYAM AZARBAYJANI
Work Adjacent to Public Way Cleared 7/15/2019 MARYAM AZARBAYJANI
City owned building/parcel Cleared 7/22/2019 HAROOT AVANESIAN
Specific Plan Cleared 8/8/2019 PEDRO AYALA
Construction near power lines Cleared 10/10/2019 WALTER RAMIREZ
DAS Clearance Cleared 10/16/2019 DEAN RYAN REYES
Hydrant and Access approval Cleared 11/22/2019 JOHN CONNEALLY
Airport buildings Cleared 12/2/2019 ANDREW KO
Low Impact Development Cleared 2/3/2020 ORVAL HERNANDEZ-MARCI
Building over 3-story or 36-ft Cleared 2/7/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 2/7/2020 CALOSHA APPROVED

Contact Information

Contractor Fluor Flatiron Balfour Beatty Dragados; Lic. No.: 1036344-B 5050 BUSINESS CENTER DRIVE   SUITE 250    FAIRFIELD, CA 94534
Engineer Chou,, Shen-Ping; Lic. No.: C51399 3861 BANYAN ST      IRVINE, CA 92606
Engineer Eaton,, Roger Anthony; Lic. No.: C76233 3102 ALGONQUIN TRAIL      LOWER BURRELL, PA 15068
Engineer Friedheim,, Marc; Lic. No.: C57968 3210 BERMUDA AVE      DAVIS, CA 95616
Engineer Harrold,, Myles Robert; Lic. No.: C64770 1401 W ROBERTA AVE      FULLERTON, CA 92833
Engineer Hatinger,, Nickolas Robert; Lic. No.: C80910 1637 9TH AVE SW      OLYMPIA, WA 98502
Engineer Norboe,, Peter William; Lic. No.: C57519 4217 WINDSONG STREET      SACRAMENTO, CA 95834
Engineer Sims,, Charles Jeff; Lic. No.: C46471 8412 RUGGLES CT      FAIR OAKS, CA 95628
Engineer Werts,, Chester Anthony; Lic. No.: C49861 5449 40TH AVE SW      OLYMPIA, WA 98512

Inspector Information

NICK LAROCCA, (213) 473-2153 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/9/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/14/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/15/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/18/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 5/21/2020 Partial Approval JONATHAN ALLEN
Piling/Pier/Caisson 6/12/2020 Partial Approval JONATHAN ALLEN
Pre-Inspection 6/29/2020 Partial Approval JONATHAN ALLEN
Pre-Inspection 6/30/2020 Approved NICK LAROCCA
Pre-Inspection 7/1/2020 Not Ready for Inspection ALBERT COMISARI
Pre-Inspection 7/25/2020 Partial Approval ALBERT COMISARI
Excavation/Setback/Form/Re-Bar 2/5/2021 Partial Approval JONATHAN ALLEN
Reinforced Concrete Frame 6/9/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/11/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/14/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/15/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/16/2021 Not Ready for Inspection JONATHAN ALLEN
Reinforced Concrete Frame 6/17/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/18/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/21/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/22/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/23/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/24/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 6/30/2021 Partial Approval JONATHAN ALLEN
Reinforced Concrete Frame 7/1/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/7/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/8/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/9/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/12/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/13/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/14/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/15/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/16/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/19/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/20/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/21/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/22/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/23/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/26/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/27/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/28/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 7/30/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 8/3/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 8/4/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 8/26/2021 Partial Approval ALAN NOVAK
Reinforced Concrete Frame 9/2/2021 Order to Comply Issued ALAN NOVAK
Reinforced Concrete Frame 4/12/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 4/19/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 5/17/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 5/18/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 5/19/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 8/17/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 8/18/2022 Partial Approval NICK LAROCCA
Reinforced Concrete Frame 9/1/2022 Partial Approval NICK LAROCCA
Final 4/18/2024 Not Ready for Inspection NICK LAROCCA
Final 9/27/2024 OK to Issue CofO NICK LAROCCA