3800 S FIGUEROA ST 90037
Certificate Information: 3800 S FIGUEROA ST 90037
- Application / Permit
- 19020-10000-01226
- Plan Check / Job No.
- B19LA08891
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- EARLY START PERMIT, SHORING FOR A 7 STORY MIXED USE RETAIL/RESIDENTIAL BUILDING
- Permit Issued
- Issued on 12/12/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2019 | LARRY LEE |
| Corrections Issued | 10/1/2019 | LARRY LEE |
| Quality Review Completed | 10/8/2019 | CHARLES CHANG |
| Building Plans Picked Up | 10/9/2019 | APPLICANT |
| Applicant returned to address corrections | 10/29/2019 | LARRY LEE |
| Plan Check Approved | 12/9/2019 | LARRY LEE |
| Issued | 12/12/2019 | LADBS |
| Permit Finaled | 1/29/2020 | JAMES POWERS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2019 | ELENA LOPEZ |
| Project located in CRA area | Cleared | 7/23/2019 | JIM URQUHART |
| Trees in Parkway | Cleared | 8/30/2019 | JOHN KIM |
| Work Adjacent to Public Way | Cleared | 9/25/2019 | BOK GOH |
| Excavation more than 5-ft deep | Cleared | 10/10/2019 | CALOSHA APPROVED |
| Address approval | Cleared | 10/15/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | THOMAS LANG |
| Highway dedication | Cleared | 10/15/2019 | THOMAS LANG |
| Permit | Cleared | 10/15/2019 | THOMAS LANG |
| Sewer availability | Cleared | 10/15/2019 | THOMAS LANG |
| CPC | Cleared | 11/6/2019 | JOE LUCKEY |
| Opn space landscape/Water mgmt | Cleared | 11/6/2019 | JOE LUCKEY |
| Site Plan review | Cleared | 11/6/2019 | JOE LUCKEY |
| ZI | Cleared | 11/6/2019 | JOE LUCKEY |
| ZI | Cleared | 11/6/2019 | JOE LUCKEY |
| ZI | Cleared | 11/6/2019 | JOE LUCKEY |
| DAS Clearance | Cleared | 11/13/2019 | LARRY LEE |
| Green Code | Cleared | 11/13/2019 | KHEDER ALRAZAA |
| Driveway location | Cleared | 11/14/2019 | MOHAMMAD HASAN |
| Internal circulation | Cleared | 11/14/2019 | MOHAMMAD HASAN |
| Miscellaneous | Cleared | 11/14/2019 | MOHAMMAD HASAN |
| Fire Marshall Fire Life Safety | Cleared | 12/5/2019 | WILLIAM JOHNS |
| Hydrant and Access approval | Cleared | 12/5/2019 | ROBERT DUFF |
| Low Impact Development | Cleared | 12/5/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/6/2019 | ELENA LOPEZ |
| Density Bonus 12.22.A.25 | Cleared | 12/9/2019 | DORIS KWOK |
Contact Information
| Contractor | A & R Corporation Inc; Lic. No.: 951076-B | 34 TALMONT NEWPORT COAST, CA 92657 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/18/2019 | Approved | JAMES POWERS |
| Deputy Grading | 12/30/2019 | Approved | JOEY BUCHANAN |
| Deputy Grading | 12/31/2019 | Approved | JOEY BUCHANAN |
| Deputy Grading | 1/2/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/6/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/7/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/8/2020 | Approved | JOEY BUCHANAN |
| Deputy Grading | 1/9/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/10/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/13/2020 | Approved | JOEY BUCHANAN |
| Deputy Grading | 1/14/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/15/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/16/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/17/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/22/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/23/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/24/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/28/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/29/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/30/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 1/31/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/3/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/4/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/5/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/6/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/7/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/10/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/11/2020 | Partial Approval | JAMES POWERS |
| Deputy Grading | 2/12/2020 | Partial Approval | JAMES POWERS |