440 E 91ST ST 90003
Certificate Information: 440 E 91ST ST 90003
- Application / Permit
- 19020-10000-01185
- Plan Check / Job No.
- B19LA08600
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- RELOCATION PERMIT FOR (E) SINGLE -FAMILY DWELLING AT 1332 W. JEFFERSON BLVD TO 440 E. 91ST STREET. PLAN CHECK FOR FOUNDATION AND ZONING ONLY.
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | KEVIN MORALES |
| Corrections Issued | 5/22/2019 | KEVIN MORALES |
| Quality Review Completed | 6/7/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 6/10/2019 | APPLICANT |
| Plan Check Approved | 8/14/2019 | KEVIN MORALES |
| Issued | 3/6/2020 | LADBS |
| CofO in Progress | 4/7/2022 | HORACE FULTZ |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
| CofO Issued | 5/7/2022 | DEROLD HAUFF |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 7/10/2019 | KEVIN MORALES |
| Community Plan Implem. Overlay | Cleared | 7/15/2019 | STEVE GARCIA |
| Low Impact Development | Cleared | 7/31/2019 | RYAN HUDSON |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 8/7/2019 | ERIK BEASLEY |
| Miscellaneous | Cleared | 8/14/2019 | STEVE GARCIA |
Contact Information
| Architect | Buser,, Bradley A; Lic. No.: C35921 | 236 FORDHAM ROAD MANHATTAN, KS 66503 |
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2020 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 5/5/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 6/9/2020 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/9/2020 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/11/2020 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 10/1/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 6/11/2021 | No Access for Inspection | ELMER BLAND |
| Wood Frame | 6/25/2021 | Corrections Issued | DAVID FEILER |
| Deputy Wood Construction | 6/28/2021 | Partial Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/29/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 6/29/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 6/29/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Final | 8/6/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/6/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Service/Power Release | 8/6/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/31/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/1/2021 | Approved | ALAN MORELOS |
| HVAC-Rough | 9/1/2021 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 9/1/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/2/2021 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/4/2022 | Not Ready for Inspection | HORACE FULTZ |
| HVAC-Final | 2/4/2022 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Final | 2/4/2022 | Not Ready for Inspection | HORACE FULTZ |
| Service/Power Release | 2/4/2022 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Final | 2/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Gas Test | 2/11/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 2/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 2/16/2022 | Not Ready for Inspection | HORACE FULTZ |
| HVAC-Final | 2/16/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 2/16/2022 | Approved | HORACE FULTZ |
| Service/Power Release | 2/16/2022 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Final | 2/23/2022 | Partial Approval | HORACE FULTZ |
| Service/Power Release | 2/23/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 3/9/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 3/14/2022 | Approved | HORACE FULTZ |
| Final | 4/6/2022 | OK to Issue CofO | HORACE FULTZ |