440 E 91ST ST 90003

Certificate Information: 440 E 91ST ST 90003

Application / Permit
19020-10000-01185
Plan Check / Job No.
B19LA08600
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
RELOCATION PERMIT FOR (E) SINGLE -FAMILY DWELLING AT 1332 W. JEFFERSON BLVD TO 440 E. 91ST STREET. PLAN CHECK FOR FOUNDATION AND ZONING ONLY.
Permit Issued
Issued on 3/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 KEVIN MORALES
Corrections Issued 5/22/2019 KEVIN MORALES
Quality Review Completed 6/7/2019 JOSE RODRIGUEZ
Building Plans Picked Up 6/10/2019 APPLICANT
Plan Check Approved 8/14/2019 KEVIN MORALES
Issued 3/6/2020 LADBS
CofO in Progress 4/7/2022 HORACE FULTZ
Permit Finaled 5/7/2022 DEROLD HAUFF
CofO Issued 5/7/2022 DEROLD HAUFF
Permit Finaled 5/7/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 7/10/2019 KEVIN MORALES
Community Plan Implem. Overlay Cleared 7/15/2019 STEVE GARCIA
Low Impact Development Cleared 7/31/2019 RYAN HUDSON
Eng Process Fee Ord 176,300 Cleared 8/7/2019 ERIK BEASLEY
Sewer availability Cleared 8/7/2019 ERIK BEASLEY
Miscellaneous Cleared 8/14/2019 STEVE GARCIA

Contact Information

Architect Buser,, Bradley A; Lic. No.: C35921 236 FORDHAM ROAD      MANHATTAN, KS 66503
Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/5/2020 Corrections Issued EUGENE CASSIDY
Pre-Inspection 5/5/2020 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 6/9/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 6/9/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/11/2020 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 10/1/2020 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 6/11/2021 No Access for Inspection ELMER BLAND
Wood Frame 6/25/2021 Corrections Issued DAVID FEILER
Deputy Wood Construction 6/28/2021 Partial Approval JOAQUIN GREENOUGH
ELECTRICAL-Rough 6/29/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 6/29/2021 Not Ready for Inspection DAVID FEILER
Wood Frame 6/29/2021 Partial Approval DAVID FEILER
ELECTRICAL-Final 8/6/2021 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 8/6/2021 Corrections Issued JOAQUIN GREENOUGH
Service/Power Release 8/6/2021 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 8/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/17/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 8/31/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 9/1/2021 Approved ALAN MORELOS
HVAC-Rough 9/1/2021 Approved ALAN MORELOS
PLUMBING-Rough 9/1/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 9/2/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Final 2/4/2022 Not Ready for Inspection HORACE FULTZ
HVAC-Final 2/4/2022 Not Ready for Inspection HORACE FULTZ
PLUMBING-Final 2/4/2022 Not Ready for Inspection HORACE FULTZ
Service/Power Release 2/4/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Final 2/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Gas Test 2/11/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 2/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 2/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Service/Power Release 2/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Final 2/16/2022 Not Ready for Inspection HORACE FULTZ
HVAC-Final 2/16/2022 Approved HORACE FULTZ
PLUMBING-Final 2/16/2022 Approved HORACE FULTZ
Service/Power Release 2/16/2022 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Final 2/23/2022 Partial Approval HORACE FULTZ
Service/Power Release 2/23/2022 Approved HORACE FULTZ
ELECTRICAL-Final 3/9/2022 Approved LILIANA PORTILLO
Service/Power Release 3/14/2022 Approved HORACE FULTZ
Final 4/6/2022 OK to Issue CofO HORACE FULTZ