11100 W PEORIA ST 91352
Certificate Information: 11100 W PEORIA ST 91352
- Application / Permit
- 19020-10000-00203
- Plan Check / Job No.
- B19LA01872
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- EARLY START PERMIT FOR SITE RETAINING WALLS With MAX. 10' IN HEIGHT FOR FILM AND TELEVISION STUDIO
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | JOSE RODRIGUEZ |
| Corrections Issued | 2/13/2019 | MOHAMMAD FIROUZBAKHT |
| Quality Review Completed | 2/15/2019 | FELIX FIGUEROA |
| Applicant returned to address corrections | 4/15/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 5/7/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 6/4/2019 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 6/24/2021 | VIVIAN LAO |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Applicant returned to address corrections | 8/31/2021 | GARO TELMI |
| Applicant returned to address corrections | 9/1/2021 | GARO TELMI |
| Applicant returned to address corrections | 9/20/2021 | GARO TELMI |
| Applicant returned to address corrections | 9/28/2021 | GARO TELMI |
| Applicant returned to address corrections | 11/4/2021 | GARO TELMI |
| Plan Check Approved | 11/5/2021 | GARO TELMI |
| Issued | 12/3/2021 | APPLICANT |
| Permit Finaled | 8/26/2024 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| ZA Case | Cleared | 3/14/2019 | ANNA VAN |
| ZA Case | Cleared | 3/14/2019 | ANNA VAN |
| ZI | Cleared | 3/14/2019 | ANNA VAN |
| Low Impact Development | Cleared | 5/7/2019 | ORVAL HERNANDEZ-MARCI |
| Stormwater Pollution Mitigatn | Cleared | 5/7/2019 | ORVAL HERNANDEZ-MARCI |
| Specific Plan | Cleared | 5/12/2021 | PEGGY MALONE-BROWN |
| CPC | Cleared | 9/23/2021 | ANNA VIDAL |
| Landscape for retaining wall | Cleared | 9/23/2021 | ANNA VIDAL |
| Landscape for retaining wall | Cleared | 9/23/2021 | ANNA VIDAL |
| Miscellaneous | Cleared | 9/23/2021 | ANNA VIDAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KITCKO, (818) 374-1109 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/22/2022 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/10/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/11/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 3/16/2022 | Approved | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/4/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/5/2022 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/12/2022 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/25/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 4/26/2022 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 5/4/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 5/5/2022 | Partial Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 5/23/2022 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 6/10/2022 | Approved | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 6/13/2022 | Partial Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 6/15/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 6/16/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 6/17/2022 | Approved | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 6/21/2022 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 6/22/2022 | Approved | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 6/27/2022 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 7/7/2022 | Partial Inspection | GREGORY POMISH |
| Deputy Reinf. Masonry | 8/15/2022 | Partial Approval | GREGORY POMISH |
| Reinforced Masonry Frame | 8/15/2022 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/29/2022 | Approved | DANNY RODRIGUEZ |
| Deputy Reinf. Concrete | 10/13/2022 | Approved | DANNY RODRIGUEZ |
| Reinforced Concrete Frame | 2/14/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | DANIEL VARNUM |
| Reinforced Masonry Frame | 3/8/2023 | Partial Approval | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 3/29/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 3/30/2023 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Reinforced Masonry Frame | 3/31/2023 | Partial Approval | DANNY RODRIGUEZ |
| Masonry Wall/Backfill | 4/18/2023 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 5/15/2023 | Conditional Approval | JOHN KITCKO |