2221 S WESTERN AVE 90018

Certificate Information: 2221 S WESTERN AVE 90018

Application / Permit
19020-10000-00108
Plan Check / Job No.
B19LA00944
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Shoring (Temporary)
Work Description
PROPOSED TEMPORARY SHORING FOR 5-STORY MIXED USE BLDG BEING ISSUED UNDER 18010-10000- 01617
Permit Issued
Issued on 2/3/2021
Issuing Office
Metro
Current Status
Permit Finaled on 11/7/2022

Permit Application Status History

Submitted 1/16/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 JOHN VASQUEZ
Corrections Issued 2/8/2019 JOHN VASQUEZ
Quality Review Completed 2/14/2019 CHARLES CHANG
Building Plans Picked Up 2/14/2019 APPLICANT
Applicant returned to address corrections 4/15/2020 JOHN VASQUEZ
Applicant returned to address corrections 4/17/2020 JOHN VASQUEZ
Applicant returned to address corrections 5/19/2020 JOHN VASQUEZ
Applicant returned to address corrections 6/10/2020 JOHN VASQUEZ
Plan Check Approved 6/26/2020 JOHN VASQUEZ
Issued 2/3/2021 APPLICANT
Permit Finaled 11/4/2022 RUSSELL BONVOULOIR

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/21/2019 ELAINE LEI
Excavation more than 5-ft deep Cleared 2/7/2020 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 4/17/2020 TERRY PHAN

Contact Information

Architect Denari,, Neil Martin; Lic. No.: C29351 NEIL M. DENARI ARCHITECTS   4335 W. ADAMS BLVD.    LOS ANGELES, CA 90018
Contractor Owner-Builder       ,
Engineer Conaway,, Johnny Ray; Lic. No.: C19689 PO BOX 155      OAK VIEW, CA 93022
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Gavazza,, Jeffrey Bryan; Lic. No.: C59894 472 35TH ST      MANHATTAN BEACH, CA 90266

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 6/18/2021 Conditional Approval RUSSELL BONVOULOIR
Pre-Inspection 6/18/2021 Partial Approval JAMES POWERS
Deputy Grading 6/21/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 6/22/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Grading 6/23/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Grading 6/24/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Grading 6/25/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Other (see comments) 6/28/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Other (see comments) 6/29/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 6/30/2021 Partial Approval JAMES POWERS
Deputy Other (see comments) 7/1/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Other (see comments) 7/2/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Grading 7/6/2021 Partial Approval JAMES POWERS
Deputy Grading 7/7/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Grading 7/8/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Grading 7/9/2021 Conditional Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 7/12/2021 Not Ready for Inspection DAVID TSAU
Final 11/4/2022 Permit Finaled RUSSELL BONVOULOIR