9805 N MASON AVE 91311

Certificate Information: 9805 N MASON AVE 91311

Application / Permit
19020-10000-00059
Plan Check / Job No.
B19LA00525
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
SITE IMPROVEMENTS FOR PARKING LOT. FOR PROPOSED BUILDING UNDER 18016-10000-36021
Permit Issued
Issued on 10/17/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 HERNAN ARREOLA
Corrections Issued 2/6/2019 HERNAN ARREOLA
Quality Review Completed 2/12/2019 BILL STUTSMAN
Building Plans Picked Up 2/15/2019 APPLICANT
Disabled Access Plans Picked Up 3/6/2019 APPLICANT
Applicant returned to address corrections 3/28/2019 HERNAN ARREOLA
Plan Check Approved 10/17/2019 HERNAN ARREOLA
Issued 10/17/2019 LADBS
CofO in Progress 3/23/2021 JEFFREY FULTON
Permit Finaled 3/26/2021 JEFFREY DURAN
CofO Issued 3/26/2021 JEFFREY DURAN
Permit Finaled 3/26/2021 JEFFREY DURAN

Permit Application Clearance Information

DAS Clearance Cleared 4/4/2019 HERNAN ARREOLA
"Q" conditions Cleared 7/2/2019 EDBER MACEDO
"T" removal Cleared 7/2/2019 EDBER MACEDO
Comm Cor/Mini-Mall Cleared 7/2/2019 EDBER MACEDO
Comm Cor/Mini-Mall Cleared 7/2/2019 EDBER MACEDO
Miscellaneous Cleared 7/2/2019 EDBER MACEDO
Miscellaneous Cleared 7/2/2019 EDBER MACEDO
Miscellaneous Cleared 7/2/2019 EDBER MACEDO
Miscellaneous Cleared 7/2/2019 EDBER MACEDO
Eng Process Fee Ord 176,300 Cleared 7/22/2019 JEANIE LAM
Permit Cleared 7/22/2019 JEANIE LAM
Driveway location Cleared 10/1/2019 BRANDON WILSON

Contact Information

Architect Mc, Kently, Kenneth; Lic. No.: C19257 1708 LAS FLORES DRIVE      GLENDALE, CA 91207
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/1/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 10/5/2020 Not Ready for Inspection JEFFREY FULTON
Final 1/13/2021 Not Ready for Inspection HAMID PISHEHVAR
Reinforced Masonry Frame 1/13/2021 Not Ready for Inspection HAMID PISHEHVAR
Structural Steel Frame 1/13/2021 Not Ready for Inspection HAMID PISHEHVAR
Final 2/26/2021 Corrections Issued JEFFREY FULTON
Reinforced Masonry Frame 2/26/2021 Approved JEFFREY FULTON
Structural Steel Frame 2/26/2021 Approved JEFFREY FULTON
Final 3/18/2021 OK to Issue CofO JEFFREY FULTON