3118 W MONT CLAIR ST 90018

Certificate Information: 3118 W MONT CLAIR ST 90018

Application / Permit
19016-70000-41379
Plan Check / Job No.
B19SL01903
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REPAIR AND REHABILITATE EXISITING 1-STORY, HISTORIC SINGLE FAMILY DWELLING. UPDATE EXISTING STRUCTURAL AND RE-ROOF. RENOVATE EXISITNG BATHROOM AND KITCHEN; EXPANDING AREA AT 2ND FLOOR ATTIC FOR NEW RESTROOM/CLOSET
Permit Issued
Issued on 9/1/2020
Issuing Office
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2020 PRANITA SHAH
Corrections Issued 2/12/2020 PRANITA SHAH
Quality Review Completed 2/13/2020 MINYE PAK
Building Plans Picked Up 2/20/2020 APPLICANT
Applicant returned to address corrections 4/8/2020 PRANITA SHAH
Green Plans Picked Up 6/10/2020 APPLICANT
Applicant returned to address corrections 7/13/2020 PRANITA SHAH
Applicant returned to address corrections 7/16/2020 PRANITA SHAH
Applicant returned to address corrections 8/5/2020 PRANITA SHAH
Applicant returned to address corrections 8/24/2020 PRANITA SHAH
Plan Check Approved 9/1/2020 PRANITA SHAH
Issued 9/1/2020 APPLICANT
CofO in Progress 5/28/2024 JUSTIN HAWLEY
Permit Finaled 6/6/2024 DEROLD HAUFF
CofO Issued 6/6/2024 DEROLD HAUFF
Permit Finaled 6/6/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 5/15/2020 LAMBERT GIESSINGER
ZI Cleared 5/15/2020 LAMBERT GIESSINGER
Green Code Cleared 6/9/2020 NEGAR NEJAD
Eng Process Fee Ord 176,300 Cleared 8/27/2020 ELENA LOPEZ
Roof/Waste drainage to street Cleared 8/27/2020 ELENA LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Green,, Melvyn; Lic. No.: S1625 5924 PACIFIC COAST HWY UNIT 9      REDONDO BEACH, CA 90277

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2020 Partial Approval STUART CHAPMAN
METHANE-Barrier 12/22/2020 Approved STUART CHAPMAN
METHANE-Subgrade 12/22/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 2/2/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/26/2021 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 4/26/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 4/26/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 4/26/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 8/18/2021 Corrections Issued WILLIAM WREN
PLUMBING-Rough 2/18/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/24/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 8/24/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Approved STUART CHAPMAN
Green Building Rough 8/24/2022 Approved STUART CHAPMAN
Shower Pan 11/1/2022 Approved STUART CHAPMAN
Insulation 11/17/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 12/1/2022 Approved CALEB MEISTER
Drywall Nailing 3/17/2023 Approved MICHAEL LEWIS
Final 5/10/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 5/10/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 5/10/2024 Not Ready for Inspection JUSTIN HAWLEY
Smoke Detectors 5/10/2024 Approved JUSTIN HAWLEY
ELECTRICAL-Final 5/28/2024 Approved JUSTIN HAWLEY
Final 5/28/2024 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 5/28/2024 Approved JUSTIN HAWLEY
HVAC-Final 5/28/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 5/28/2024 Approved JUSTIN HAWLEY
Service/Power Release 5/28/2024 Approved JUSTIN HAWLEY