960 E 3RD ST 90013
Certificate Information: 960 E 3RD ST 90013
- Application / Permit
- 19016-70000-41045
- Plan Check / Job No.
- B19SL01860
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) School - professional or scientific
- Work Description
- NEW FABRIC STRUCTURE ACCESSORY TO AN (E) PROFESSIONAL SCHOOL TO BE USED AS A FABRICATION FACILITY.
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- Issued on 8/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2020 | LUKE GONZALES |
| Corrections Issued | 3/19/2020 | LUKE GONZALES |
| Quality Review Completed | 3/23/2020 | TEODORO DIAZ RODRIGUEZ |
| Green Plans Picked Up | 4/24/2020 | APPLICANT |
| Applicant returned to address corrections | 10/16/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 1/22/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 3/18/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 5/26/2021 | LUKE GONZALES |
| Plan Check Approved | 6/15/2021 | LUKE GONZALES |
| Issued | 8/13/2021 | APPLICANT |
| Building Plans Picked Up | 8/16/2021 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 3/5/2020 | KHEDER ALRAZAA |
| City Hist. Cultural Monument | Cleared | 6/9/2020 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 6/9/2020 | LAMBERT GIESSINGER |
| ZA Case | Cleared | 6/12/2020 | MAXFIELD VERMY |
| ZI | Cleared | 6/12/2020 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | CELINA MORENO |
| Highway dedication | Cleared | 7/21/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 8/6/2020 | MATTHEW CRAIG |
| Metro Rail approval | Cleared | 8/24/2020 | LUKE GONZALES |
| Low Impact Development | Cleared | 9/22/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 9/29/2020 | CELINA MORENO |
| ZI | Cleared | 11/10/2020 | MAXFIELD VERMY |
| Sewer availability | Cleared | 3/8/2021 | CECILIO NAVARRO |
| Fire Marshall Fire Life Safety | Cleared | 3/17/2021 | DOMINIQUE MEDINA |
| DAS Clearance | Cleared | 6/10/2021 | EDDIE GARIN |
Contact Information
| Architect | Gedgaudas,, Augis J; Lic. No.: C26473 | 1167 GALLOWAY STREET PACIFIC PALISADES, CA 90272 |
| Contractor | Swinerton Builders; Lic. No.: 92-B | 2001 CLAYTON RD 7TH FLOOR LEGAL CONCORD, CA 94520 |
| Engineer | Mcginnis,, Daniel Warren; Lic. No.: S5324 | 1110 WESTMARK DR SAINT LOUIS, MO 63131 |
| Engineer | Vertrees,, Joseph Henry; Lic. No.: C51908 | 532 E LAMBERT RD BREA, CA 92821 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/20/2021 | Partial Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Corrections Issued | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 8/23/2021 | Approved | RAFAEL ESPINOZA |
| METHANE-Barrier | 8/23/2021 | Approved | RAFAEL ESPINOZA |
| METHANE-Final | 8/23/2021 | Approved | RAFAEL ESPINOZA |
| METHANE-Rough | 8/23/2021 | Approved | RAFAEL ESPINOZA |
| METHANE-Subgrade | 8/23/2021 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 8/24/2021 | Conditional Approval | LANNY MERRICK |
| Final | 11/1/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Green Building Final | 11/1/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Green Building Rough | 11/1/2021 | Approved | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV No Gas | DANIEL COLLINS |
| Smoke Detectors | 11/1/2021 | Approved | DANIEL COLLINS |
| Verify Sprinkler Sign Off | 11/1/2021 | Approved | DANIEL COLLINS |
| Wood Frame | 11/1/2021 | Approved | DANIEL COLLINS |
| Final | 12/6/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Special/Order Compliance | 12/6/2021 | Approved | KATY RAMIREZ |
| Final | 12/10/2021 | Conditional Approval | MARK FERRARI |
| Green Building Final | 12/10/2021 | Approved | MARK FERRARI |
| Final | 1/31/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 7/2/2024 | Conditional Approval | RONALD JIMENEZ |