1815-1815 1/2 W 36TH ST 90018
Certificate Information: 1815-1815 1/2 W 36TH ST 90018
- Application / Permit
- 19016-70000-36320
- Plan Check / Job No.
- B19SL01576
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED NEW 3 STORY DUPLEX WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | LUKE GONZALES |
| Green Plans Picked Up | 11/21/2019 | APPLICANT |
| Corrections Issued | 12/2/2019 | LUKE GONZALES |
| Quality Review Completed | 12/3/2019 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/21/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 11/12/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 6/2/2021 | LUKE GONZALES |
| Plan Check Approved | 8/12/2021 | LUKE GONZALES |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 8/9/2024 | SABAS ALONSO |
| CofO Issued | 8/28/2024 | RUBEN SALAS |
| Permit Finaled | 8/28/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2019 | THOMAS LANG |
| Green Code | Cleared | 3/6/2020 | NEGAR NEJAD |
| ZI | Cleared | 5/28/2020 | DANIEL CORONADO |
| Permit | Cleared | 7/20/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | JEANIE LAM |
| Sewer availability | Cleared | 8/4/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 8/17/2020 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 8/24/2020 | JOHN KIM |
| Low Impact Development | Cleared | 9/21/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/28/2020 | JAMES KHO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 4/11/2023 | Approved | SABAS ALONSO |
| METHANE-Barrier | 4/11/2023 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 4/11/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 4/18/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 4/19/2023 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 4/19/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 4/21/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 12/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 12/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 12/6/2023 | Corrections Issued | SABAS ALONSO |
| METHANE-Rough | 12/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/6/2023 | Corrections Issued | SABAS ALONSO |
| Verify Sprinkler Sign Off | 12/6/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 12/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/27/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/27/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 12/27/2023 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 12/27/2023 | Approved | SABAS ALONSO |
| Wood Frame | 12/27/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/28/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 12/28/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/28/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 12/28/2023 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 12/28/2023 | Approved | SABAS ALONSO |
| Wood Frame | 12/28/2023 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 1/4/2024 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/9/2024 | Approved | SABAS ALONSO |
| Insulation | 1/9/2024 | Approved | SABAS ALONSO |
| METHANE-Rough | 1/9/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 1/9/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 1/16/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/16/2024 | Approved | SABAS ALONSO |
| Shower Pan | 1/16/2024 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 1/17/2024 | Approved | SABAS ALONSO |
| Shower Pan | 1/17/2024 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 1/26/2024 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 2/1/2024 | No Access for Inspection | MICHAEL LEWIS |
| Sewer | 3/6/2024 | Approved | SABAS ALONSO |
| Shower Pan | 3/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 3/26/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/14/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 6/14/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/14/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 6/14/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 6/14/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 6/14/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 6/14/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 6/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 6/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 7/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 7/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 7/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 7/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 7/18/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 7/22/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 7/22/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 7/22/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 7/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 8/2/2024 | Approved | SABAS ALONSO |
| Final | 8/2/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 8/2/2024 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 8/2/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 8/6/2024 | Approved | SABAS ALONSO |
| Final | 8/6/2024 | Corrections Issued | SABAS ALONSO |
| Gas Test | 8/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 8/6/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 8/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 8/8/2024 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 8/8/2024 | Approved | SABAS ALONSO |