4332 S LIMA ST 90011
Certificate Information: 4332 S LIMA ST 90011
- Application / Permit
- 19016-70000-34489
- Plan Check / Job No.
- B19SL01486
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) GARAGE INTO ADU PER AB494 AND SB229 *COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 09/17/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSURANCE DATE*
- Permit Issued
- Issued on 2/13/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | FERNANDO FLORES |
| Corrections Issued | 11/14/2019 | FERNANDO FLORES |
| Quality Review Completed | 11/25/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 12/11/2019 | APPLICANT |
| Applicant returned to address corrections | 12/23/2019 | FERNANDO FLORES |
| Applicant returned to address corrections | 1/2/2020 | FERNANDO FLORES |
| Green Plans Picked Up | 1/10/2020 | APPLICANT |
| Plan Check Approved | 2/7/2020 | FERNANDO FLORES |
| Issued | 2/13/2020 | LADBS |
| CofO in Progress | 6/24/2021 | MARIO CUEVAS |
| Permit Finaled | 7/14/2021 | BRUCE TODD |
| CofO Issued | 7/14/2021 | BRUCE TODD |
| Permit Finaled | 7/14/2021 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/30/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 1/28/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 2/7/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/7/2020 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mokri-Arganeh,, Fattaneh; Lic. No.: C52608 | 2075 S COUNTRY CYN RD HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| JEREMY TODD, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARVIN FONSECA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GUEVARA, (213) 978-4495 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2020 | Approved | MARIO CUEVAS |
| Footing/Foundation/Slab | 4/3/2020 | Corrections Issued | HECTOR RODRIGUEZ |
| Footing/Foundation/Slab | 4/8/2020 | Approved | MARIO CUEVAS |
| BUILDING-Rough-Frame | 6/10/2020 | Corrections Issued | MARIO CUEVAS |
| ELECTRICAL-Rough | 6/10/2020 | Corrections Issued | MARIO CUEVAS |
| Green Building Rough | 6/10/2020 | Not Ready for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 6/10/2020 | Corrections Issued | MARIO CUEVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Approved | MARIO CUEVAS |
| BUILDING-Rough-Frame | 6/24/2020 | No Access for Inspection | MARIO CUEVAS |
| ELECTRICAL-Rough | 6/24/2020 | No Access for Inspection | MARIO CUEVAS |
| Green Building Rough | 6/24/2020 | No Access for Inspection | MARIO CUEVAS |
| HVAC-Rough | 6/24/2020 | No Access for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 6/24/2020 | No Access for Inspection | MARIO CUEVAS |
| BUILDING-Rough-Frame | 6/25/2020 | Not Ready for Inspection | MARIO CUEVAS |
| ELECTRICAL-Rough | 6/25/2020 | Corrections Issued | MARIO CUEVAS |
| Green Building Rough | 6/25/2020 | Not Ready for Inspection | MARIO CUEVAS |
| HVAC-Rough | 6/25/2020 | Not Ready for Inspection | MARIO CUEVAS |
| PLUMBING-Rough | 6/25/2020 | Corrections Issued | MARIO CUEVAS |
| BUILDING-Rough-Frame | 7/21/2020 | Approved | MARIO CUEVAS |
| ELECTRICAL-Rough | 7/21/2020 | Corrections Issued | MARIO CUEVAS |
| Green Building Rough | 7/21/2020 | Approved | MARIO CUEVAS |
| HVAC-Rough | 7/21/2020 | Corrections Issued | MARIO CUEVAS |
| PLUMBING-Rough | 7/21/2020 | Corrections Issued | MARIO CUEVAS |
| ELECTRICAL-Rough | 8/10/2020 | Approved | MARIO CUEVAS |
| HVAC-Rough | 8/10/2020 | Corrections Issued | MARIO CUEVAS |
| PLUMBING-Rough | 8/10/2020 | Partial Approval | MARIO CUEVAS |
| Rough-Elec/Plmb/HVAC | 9/29/2020 | Approved | MARIO CUEVAS |
| Insulation | 10/1/2020 | Approved | MARIO CUEVAS |
| Drywall Nailing | 10/29/2020 | Approved | MARIO CUEVAS |
| Interior/Exterior Lathing | 10/29/2020 | Approved | MARIO CUEVAS |
| Sewer | 10/29/2020 | Approved | MARIO CUEVAS |
| Final | 6/8/2021 | Corrections Issued | MARIO CUEVAS |
| Green Building Final | 6/8/2021 | Approved | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Approved | MARIO CUEVAS |
| Smoke Detectors | 6/8/2021 | Corrections Issued | MARIO CUEVAS |
| Final | 6/23/2021 | Partial Approval | MARIO CUEVAS |
| Smoke Detectors | 6/23/2021 | Approved | MARIO CUEVAS |