10437 W NORTHVALE ROAD 90064

Certificate Information: 10437 W NORTHVALE ROAD 90064

Application / Permit
19016-70000-33653
Plan Check / Job No.
B19SL01453
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF (E) BASEMENT INTO ADU PER AB494 AND SB229.
Permit Issued
Issued on 6/2/2020
Issuing Office
Current Status
Issued on 12/8/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/21/2019 APPLICANT
Assigned to Plan Check Engineer 10/21/2019 LUKE GONZALES
Corrections Issued 10/21/2019 LUKE GONZALES
Plan Check Approved 11/5/2019 TEODORO DIAZ RODRIGUEZ
Issued 6/2/2020 APPLICANT
CofO in Progress 12/28/2020 KEVIN SARGSYAN
No Progress 12/8/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 10/21/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/21/2019 JEANIE LAM
Hydrant and Access approval Cleared 10/21/2019 JOHN CONNEALLY
Sewer availability Cleared 10/21/2019 JEANIE LAM
Specific Plan Cleared 10/21/2019 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/7/2020 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 7/7/2020 Not Ready for Inspection KEVIN SARGSYAN
Insulation 7/7/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 7/7/2020 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 7/10/2020 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 7/21/2020 Not Ready for Inspection KEVIN SARGSYAN
Insulation 7/21/2020 Partial Approval KEVIN SARGSYAN
HVAC-Rough 7/28/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 8/5/2020 No Access for Inspection KEVIN SARGSYAN
HVAC-Rough 8/5/2020 No Access for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 8/10/2020 Approved KEVIN SARGSYAN
HVAC-Rough 8/10/2020 Approved KEVIN SARGSYAN
Drywall Nailing 8/14/2020 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/5/2020 SGSOV Not Ready KEVIN SARGSYAN
BUILDING-Rough-Frame 10/19/2020 Approved KEVIN SARGSYAN
MERV13>=Rough 10/19/2020 Approved KEVIN SARGSYAN
PLUMBING-Final 10/19/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 10/27/2020 Corrections Issued KEVIN SARGSYAN
HVAC-Final 10/27/2020 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/27/2020 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 10/27/2020 Approved KEVIN SARGSYAN
Final 11/19/2020 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 12/21/2020 Approved KEVIN SARGSYAN
PLUMBING-Final 12/21/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/28/2020 Approved KEVIN SARGSYAN
Final 12/28/2020 OK to Issue CofO KEVIN SARGSYAN
MERV13>=Final 12/28/2020 Approved KEVIN SARGSYAN