10437 W NORTHVALE ROAD 90064
Certificate Information: 10437 W NORTHVALE ROAD 90064
- Application / Permit
- 19016-70000-33653
- Plan Check / Job No.
- B19SL01453
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF (E) BASEMENT INTO ADU PER AB494 AND SB229.
- Permit Issued
- Issued on 6/2/2020
- Issuing Office
- Current Status
- Issued on 12/8/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2019 | LUKE GONZALES |
| Corrections Issued | 10/21/2019 | LUKE GONZALES |
| Plan Check Approved | 11/5/2019 | TEODORO DIAZ RODRIGUEZ |
| Issued | 6/2/2020 | APPLICANT |
| CofO in Progress | 12/28/2020 | KEVIN SARGSYAN |
| No Progress | 12/8/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2019 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 10/21/2019 | JOHN CONNEALLY |
| Sewer availability | Cleared | 10/21/2019 | JEANIE LAM |
| Specific Plan | Cleared | 10/21/2019 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/7/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 7/7/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 7/7/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/7/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/10/2020 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/21/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 7/21/2020 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 7/28/2020 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/5/2020 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 8/5/2020 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/10/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 8/10/2020 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 8/14/2020 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Not Ready | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/19/2020 | Approved | KEVIN SARGSYAN |
| MERV13>=Rough | 10/19/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 10/19/2020 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 10/27/2020 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 10/27/2020 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2020 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 10/27/2020 | Approved | KEVIN SARGSYAN |
| Final | 11/19/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 12/21/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 12/21/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/28/2020 | Approved | KEVIN SARGSYAN |
| Final | 12/28/2020 | OK to Issue CofO | KEVIN SARGSYAN |
| MERV13>=Final | 12/28/2020 | Approved | KEVIN SARGSYAN |