813 E 118TH PL 90059
Certificate Information: 813 E 118TH PL 90059
- Application / Permit
- 19016-70000-27194
- Plan Check / Job No.
- B19SL01166
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. REMODEL.
- Permit Issued
- Issued on 2/3/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 5/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2019 | RICARDO RAMIREZ |
| Corrections Issued | 8/28/2019 | RICARDO RAMIREZ |
| Plan Check Approved | 11/27/2019 | TEODORO DIAZ RODRIGUEZ |
| Issued | 2/3/2020 | LADBS |
| CofO in Progress | 5/5/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/20/2022 | DEROLD HAUFF |
| CofO Issued | 5/20/2022 | DEROLD HAUFF |
| Permit Finaled | 5/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/3/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/3/2019 | ERIK BEASLEY |
| ZI | Cleared | 9/3/2019 | ANNA VAN |
| Hydrant and Access approval | Cleared | 9/4/2019 | JEREMY CARTER |
| Construction near power lines | Cleared | 11/24/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Deputy Drilled-In Anchors | 3/25/2020 | Conditional Approval | BRIAN CHRISTIAN |
| Footing/Foundation/Slab | 3/26/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 3/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 3/26/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/13/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 5/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 5/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/8/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 9/8/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Rough | 9/8/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/18/2020 | Approved | DAVID FEILER |
| Green Building Rough | 9/18/2020 | Approved | DAVID FEILER |
| MERV13>=Rough | 9/18/2020 | Approved | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 9/18/2020 | Approved | DAVID FEILER |
| Insulation | 10/8/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/8/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/10/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/30/2020 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 12/30/2020 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 5/27/2021 | Partial Approval | JOHN KLARIN |
| Sewer | 6/29/2021 | Approved | DAVID FEILER |
| Final | 3/31/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 3/31/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 3/31/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/31/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/25/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 4/25/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Approved | JOHN KLARIN |
| ELECTRICAL-Final | 5/5/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/5/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 5/5/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/5/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/5/2022 | Approved | ALIZAH MAYAGOITIA |