813 E 118TH PL 90059

Certificate Information: 813 E 118TH PL 90059

Application / Permit
19016-70000-27194
Plan Check / Job No.
B19SL01166
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. REMODEL.
Permit Issued
Issued on 2/3/2020
Issuing Office
San Pedro
Current Status
CofO Issued on 5/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2019 APPLICANT
Assigned to Plan Check Engineer 8/28/2019 RICARDO RAMIREZ
Corrections Issued 8/28/2019 RICARDO RAMIREZ
Plan Check Approved 11/27/2019 TEODORO DIAZ RODRIGUEZ
Issued 2/3/2020 LADBS
CofO in Progress 5/5/2022 ALIZAH MAYAGOITIA
Permit Finaled 5/20/2022 DEROLD HAUFF
CofO Issued 5/20/2022 DEROLD HAUFF
Permit Finaled 5/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/3/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 9/3/2019 ERIK BEASLEY
Sewer availability Cleared 9/3/2019 ERIK BEASLEY
ZI Cleared 9/3/2019 ANNA VAN
Hydrant and Access approval Cleared 9/4/2019 JEREMY CARTER
Construction near power lines Cleared 11/24/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/24/2020 Corrections Issued BRIAN CHRISTIAN
Deputy Drilled-In Anchors 3/25/2020 Conditional Approval BRIAN CHRISTIAN
Footing/Foundation/Slab 3/26/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 3/26/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 3/26/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/13/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 5/13/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 5/13/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/8/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 9/8/2020 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Rough 9/8/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 9/18/2020 Approved DAVID FEILER
Green Building Rough 9/18/2020 Approved DAVID FEILER
MERV13>=Rough 9/18/2020 Approved DAVID FEILER
Rough-Elec/Plmb/HVAC 9/18/2020 Approved DAVID FEILER
Insulation 10/8/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/8/2020 Approved EUGENE CASSIDY
Drywall Nailing 11/10/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 12/30/2020 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 12/30/2020 Corrections Issued EUGENE CASSIDY
Gas Test 5/27/2021 Partial Approval JOHN KLARIN
Sewer 6/29/2021 Approved DAVID FEILER
Final 3/31/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 3/31/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 3/31/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/31/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 3/31/2022 Approved ALIZAH MAYAGOITIA
Final 4/25/2022 Not Ready for Inspection JOHN KLARIN
Green Building Final 4/25/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Approved JOHN KLARIN
ELECTRICAL-Final 5/5/2022 Approved ALIZAH MAYAGOITIA
Final 5/5/2022 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 5/5/2022 Approved ALIZAH MAYAGOITIA
HVAC-Final 5/5/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/5/2022 Approved ALIZAH MAYAGOITIA