1839 S STEARNS DR 90035

Certificate Information: 1839 S STEARNS DR 90035

Application / Permit
19016-70000-15650
Plan Check / Job No.
B19SL00683
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE EXISTING GARAGE TO AN ADU PER SB 229AND AB 494. ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 1/31/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2019 APPLICANT
Assigned to Plan Check Engineer 5/24/2019 WESLEY FARRELL
Corrections Issued 5/24/2019 WESLEY FARRELL
Applicant returned to address corrections 12/24/2019 ZAW HAN
Plan Check Approved 1/31/2020 ZAW HAN
Issued 1/31/2020 LADBS
CofO in Progress 12/15/2022 JOSE AVILA
Permit Finaled 1/7/2023 DEROLD HAUFF
CofO Issued 1/7/2023 DEROLD HAUFF
Permit Finaled 1/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 10/1/2019 RIDWAN HARDY
Construction within easement Cleared 10/1/2019 RIDWAN HARDY
Address approval Cleared 11/6/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/6/2019 ERIK BEASLEY
Sewer availability Cleared 11/6/2019 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/16/2020 Conditional Approval MATTHEW NUCKOLLS
BUILDING-Rough-Frame 3/27/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 4/9/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 7/8/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 3/4/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 3/22/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 4/20/2022 Approved JOSE AVILA
ELECTRICAL-Rough 5/11/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/31/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 6/7/2022 Approved JOSE AVILA
Special/Order Compliance 7/29/2022 Partial Inspection RUBEN SALAS
Deputy Drilled-In Anchors 8/19/2022 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 8/22/2022 Corrections Issued JOSE AVILA
Deputy Wood Construction 8/23/2022 Conditional Approval JOSE AVILA
BUILDING-Rough-Frame 9/13/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 9/15/2022 Approved JOSE AVILA
Insulation 9/15/2022 Approved JOSE AVILA
Insulation 9/20/2022 Approved JOSE AVILA
Interior/Exterior Lathing 10/5/2022 Approved JOSE AVILA
HVAC-Final 10/13/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 10/13/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 10/13/2022 Corrections Issued JOSE AVILA
Final 10/26/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 10/26/2022 Approved JOSE AVILA
Final 12/9/2022 OK to Issue CofO JOSE AVILA