1849 W 75TH ST 90047

Certificate Information: 1849 W 75TH ST 90047

Application / Permit
19016-70000-11555
Plan Check / Job No.
B19SL00492
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE 1ST FLOOR OF AN EXISTING 2-STORY SINGLE FAMILY DWELLING INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. NEW EXTERIOR STAIR AT REAR.
Permit Issued
Issued on 7/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2019 APPLICANT
Assigned to Plan Check Engineer 7/8/2020 LUKE GONZALES
Plan Check Approved 7/8/2020 LUKE GONZALES
Issued 7/23/2020 APPLICANT
Building Plans Picked Up 7/28/2020 APPLICANT
CofO in Progress 2/2/2021 FREDDIE RIVERA
Permit Finaled 5/8/2021 DEROLD HAUFF
CofO Issued 5/8/2021 DEROLD HAUFF
Permit Finaled 5/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/13/2020 JAMES MORALEZ
Hydrant and Access approval Cleared 4/9/2020 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 4/10/2020 THOMAS LANG
Sewer availability Cleared 5/13/2020 JEANIE LAM

Contact Information

Contractor James Terry R; Lic. No.: 572426-B 6226 ACACIA ST      LOS ANGELES, CA 90056
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/11/2020 Approved FREDDIE RIVERA
Drywall Nailing 9/4/2020 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 9/17/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/17/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 9/17/2020 Approved FREDDIE RIVERA
Drywall Nailing 9/22/2020 Approved FREDDIE RIVERA
HVAC-Rough 9/22/2020 Corrections Issued FREDDIE RIVERA
HVAC-Rough 9/28/2020 Approved FREDDIE RIVERA
Final 12/14/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/14/2020 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 12/14/2020 Corrections Issued FREDDIE RIVERA
Final 12/24/2020 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 12/24/2020 Approved FREDDIE RIVERA
Final 2/2/2021 OK to Issue CofO FREDDIE RIVERA