2106 1/2 W 80TH ST 90047

Certificate Information: 2106 1/2 W 80TH ST 90047

Application / Permit
19016-70000-01034
Plan Check / Job No.
B19SL00041
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 ADAM HEGAZI
Corrections Issued 2/1/2019 ADAM HEGAZI
Quality Review Completed 2/4/2019 MOHAMMAD FIROUZBAKHT
Applicant returned to address corrections 5/3/2019 ADAM HEGAZI
Applicant returned to address corrections 5/6/2019 ADAM HEGAZI
Plan Check Approved 5/10/2019 ADAM HEGAZI
Issued 9/8/2021 APPLICANT
Building Plans Picked Up 9/10/2021 APPLICANT
CofO in Progress 4/16/2026 SALVADOR MARTINEZ
Permit Finaled 4/16/2026 DEROLD HAUFF
CofO Issued 4/16/2026 DEROLD HAUFF
Permit Finaled 4/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/27/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 3/27/2019 ADRIAN SANCHEZ
Sewer availability Cleared 3/27/2019 ADRIAN SANCHEZ
Construction near power lines Cleared 4/23/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 4/23/2019 ADRIAN SANCHEZ
Green Code Cleared 5/7/2019 SARAH ABOULHOSN

Contact Information

Contractor Grace Builders International; Lic. No.: 597449-B 4854 PRESIDIO DRIVE      LOS ANGELES, CA 90043
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/18/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 2/25/2022 Corrections Issued FREDDIE RIVERA
Pre-Inspection 3/3/2022 Approved FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 3/8/2022 Not Ready for Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 3/16/2022 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 4/5/2022 Approved ENRIQUE MIRELES
Wood Frame 10/26/2022 Approved RYAN SALAZAR
Final 5/9/2024 Corrections Issued JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Corrections Issued JOSE MACIAS
Insulation 5/9/2024 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 5/9/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Approved JOSE MACIAS
Insulation 6/13/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 6/13/2024 Approved JOSE MACIAS
Drywall Nailing 7/23/2024 Approved JOSE MACIAS
Green Building Rough 7/23/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 5/7/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 2/10/2026 Approved SALVADOR MARTINEZ
Final 2/10/2026 Corrections Issued SALVADOR MARTINEZ
Green Building Final 2/10/2026 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 2/10/2026 Approved SALVADOR MARTINEZ
Final 4/15/2026 OK to Issue CofO SALVADOR MARTINEZ
Green Building Final 4/15/2026 Approved SALVADOR MARTINEZ