3521 N FIGUEROA ST 90065

Certificate Information: 3521 N FIGUEROA ST 90065

Application / Permit
19016-40000-41083
Plan Check / Job No.
B19SP01939
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
Interior & exterior alteration to (E) church. Scope of work to include installing non-load bearing partitions to create new rooms and DAS upgrades. Restripe parking area to provide 1 Van accessible H/C stall, remove 1 standard stall, convert 1 standard stall to compact ; total parking provided 15 (6 standard , 8 compact , 1 H/C)
Permit Issued
Issued on 6/15/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 REZA HAGHIGHAT
Corrections Issued 2/21/2020 REZA HAGHIGHAT
Quality Review Completed 2/28/2020 KAMRAN GHOTBI RAVANDI
Disabled Access Plans Picked Up 3/2/2020 APPLICANT
Building Plans Picked Up 3/3/2020 APPLICANT
Green Plans Picked Up 3/3/2020 APPLICANT
Applicant returned to address corrections 12/23/2022 CHIHARU SUZUKI
Plan Check Approved 2/1/2023 REZA HAGHIGHAT
Issued 6/15/2023 APPLICANT
CofO in Progress 1/6/2025 RONALD JIMENEZ
Permit Finaled 1/6/2025 ERNESTO CORRAL
CofO Issued 1/6/2025 ERNESTO CORRAL
Permit Finaled 1/6/2025 ERNESTO CORRAL

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 3/10/2020 DOMINIQUE MEDINA
Green Code Cleared 6/7/2022 RICHARD GARCIA
DAS Clearance Cleared 8/4/2022 REZA HAGHIGHAT
Supp. Use District POD/CDO/TDO Cleared 12/5/2022 NASHYA JENSEN

Contact Information

Architect Mcgrath,, James C; Lic. No.: C31946 33571 A DANA VISTA DRIVE      DANA POINT, CA 92629
Contractor Johnson Steel Source; Lic. No.: 797977-B P O BOX 93292      PASADENA, CA 911093292
Engineer Hacker,, Michael David; Lic. No.: C55606 777 E TAHQUITZ CANYON WAY STE 200-50      PALM SPRINGS, CA 92262

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2024 Partial Inspection RAMAZANALI ALMASI
Final 6/11/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 6/11/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Rough 6/11/2024 Not Ready for Inspection RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Not Ready RONALD JIMENEZ
Smoke Detectors 6/11/2024 Not Ready for Inspection RONALD JIMENEZ
Wood Frame 6/11/2024 Not Ready for Inspection RONALD JIMENEZ
Pre-Inspection 7/18/2024 Partial Inspection RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 7/25/2024 Not Ready for Inspection RONALD JIMENEZ
Green Building Rough 7/25/2024 Approved RONALD JIMENEZ
Wood Frame 7/25/2024 Not Ready for Inspection RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 7/26/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 8/2/2024 Conditional Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 8/2/2024 Partial Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 8/8/2024 Conditional Approval RAMAZANALI ALMASI
Wood Frame 8/8/2024 Corrections Issued RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 8/15/2024 Partial Approval RAMAZANALI ALMASI
Wood Frame 9/6/2024 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 9/12/2024 Partial Inspection RAMAZANALI ALMASI
Insulation 9/12/2024 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 9/12/2024 Partial Approval RAMAZANALI ALMASI
Insulation 10/8/2024 Approved RAMAZANALI ALMASI
Wood Frame 10/8/2024 Approved RAMAZANALI ALMASI
Drywall Nailing 10/11/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 10/16/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 10/30/2024 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 10/30/2024 Approved RAMAZANALI ALMASI
T-Bar Ceiling 11/26/2024 Approved RONALD JIMENEZ
Final 12/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 12/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 12/13/2024 SGSOV No Gas RAMAZANALI ALMASI
Smoke Detectors 12/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 12/31/2024 OK to Issue CofO RONALD JIMENEZ
Green Building Final 12/31/2024 Approved RONALD JIMENEZ
Smoke Detectors 12/31/2024 Approved RONALD JIMENEZ