322 W 15TH ST 90731

Certificate Information: 322 W 15TH ST 90731

Application / Permit
19016-40000-39533
Plan Check / Job No.
B19SP01874
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Retail Building to accessory dwelling unit . see comment
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 5/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 TARIK SAOUD
Corrections Issued 12/30/2019 TARIK SAOUD
Quality Review Completed 1/3/2020 FELIX FIGUEROA
Applicant returned to address corrections 4/15/2020 TARIK SAOUD
Applicant returned to address corrections 4/22/2020 TARIK SAOUD
Building Plans Picked Up 4/22/2020 APPLICANT
Plan Check Approved 1/5/2021 TARIK SAOUD
Issued 2/5/2021 APPLICANT
CofO in Progress 4/29/2021 JOHN KLARIN
No Progress 5/10/2021 ANSON MAGLASANG
CofO in Progress 5/10/2021 ANSON MAGLASANG
CofO in Progress 5/14/2021 ANSON MAGLASANG
Permit Finaled 5/19/2021 DEROLD HAUFF
CofO Issued 5/19/2021 DEROLD HAUFF
Permit Finaled 5/19/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/6/2020 CELINA MORENO
Permit Cleared 4/6/2020 CELINA MORENO
Sewer availability Cleared 4/6/2020 CELINA MORENO
Tenant Habitability Plan Cleared 4/6/2020 STEVEN HOFSTAD
Trees in Parkway Cleared 4/14/2020 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 4/22/2020 PAMELA TENEZA
Coastal Zone Cleared 11/24/2020 JEANALEE OBERGFELL
Specific Plan Cleared 11/24/2020 JEANALEE OBERGFELL

Contact Information

Architect Puskar,, Heidi M; Lic. No.: C28223 29431 N ENROSE AVENUE      RANCHO PALOS VERDES, CA 90275
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/12/2021 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 2/12/2021 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 2/12/2021 Corrections Issued JOHN KLARIN
PLUMBING-Rough 2/12/2021 Not Ready for Inspection JOHN KLARIN
Deputy Drilled-In Anchors 2/23/2021 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 3/1/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 3/8/2021 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 3/8/2021 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 3/8/2021 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 3/15/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/19/2021 Approved JOHN KLARIN
Final 4/19/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 4/19/2021 Approved JOHN KLARIN
ELECTRICAL-Final 4/28/2021 Approved JOHN KLARIN
Final 4/28/2021 OK to Issue CofO JOHN KLARIN
HVAC-Final 4/28/2021 Approved JOHN KLARIN
PLUMBING-Final 4/28/2021 Approved JOHN KLARIN