1032 N BAY VIEW AVE 90744

Certificate Information: 1032 N BAY VIEW AVE 90744

Application / Permit
19016-40000-39508
Plan Check / Job No.
B19SP01872
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) 3 unit apartment with attached garage to SFD with attached garage. All work per engineered design.
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
CofO Issued on 7/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 JASON JANGADA
Corrections Issued 1/8/2020 JASON JANGADA
Quality Review Completed 1/9/2020 CHRISTOPHER KOMANCHECK
Plan Check Approved 8/4/2021 JASON JANGADA
Building Plans Picked Up 8/6/2021 APPLICANT
Issued 8/16/2021 APPLICANT
CofO in Progress 7/12/2023 EUGENE CASSIDY
Permit Finaled 7/27/2023 ANSON MAGLASANG
CofO Issued 7/27/2023 ANSON MAGLASANG
Permit Finaled 7/27/2023 ANSON MAGLASANG

Permit Application Clearance Information

Clean Up Green Up Cleared 1/22/2020 KIT AWAKUNI
ZI Cleared 1/22/2020 KIT AWAKUNI
Tenant Habitability Plan Cleared 6/22/2021 RICARDO BOHORQUEZ
Demo/Removal of Rental Units Cleared 7/19/2021 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 7/27/2021 ERIK BEASLEY
Sewer availability Cleared 7/27/2021 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/13/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/14/2022 Not Ready for Inspection JOEY BUCHANAN
METHANE-Rough 7/14/2022 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 7/15/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/21/2022 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Partial Approval EUGENE CASSIDY
Deck 9/6/2022 Partial Inspection EUGENE CASSIDY
Pre-Inspection 9/6/2022 Approved EUGENE CASSIDY
ELECTRICAL-Rough 9/23/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 10/7/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/1/2022 Corrections Issued EUGENE CASSIDY
Deck 11/1/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 11/1/2022 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 11/1/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 11/1/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 11/1/2022 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 11/1/2022 Not Ready for Inspection EUGENE CASSIDY
Deputy Wood Construction 11/9/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/10/2022 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 11/17/2022 Approved EUGENE CASSIDY
Insulation 11/22/2022 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 11/22/2022 Partial Approval EUGENE CASSIDY
Insulation 11/30/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 11/30/2022 Approved JOHN KLARIN
Drywall Nailing 12/8/2022 Partial Approval EUGENE CASSIDY
Drywall Nailing 12/22/2022 Approved JOHN KLARIN
ELECTRICAL-Final 5/31/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 6/29/2023 Approved EUGENE CASSIDY
Final 6/29/2023 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 6/29/2023 Approved EUGENE CASSIDY
Final 7/11/2023 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 7/11/2023 Approved EUGENE CASSIDY
PLUMBING-Final 7/11/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Approved EUGENE CASSIDY