19839-19841 W STRATHERN ST 91306

Certificate Information: 19839-19841 W STRATHERN ST 91306

Application / Permit
19016-40000-38886
Plan Check / Job No.
B19SP01850
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) attached garage to Accessory Dwelling Unit per SB229 and AB494. All work per WFPP.
Permit Issued
Issued on 3/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/31/2019 MANUEL GARCIA
Green Plans Picked Up 1/9/2020 APPLICANT
Corrections Issued 1/21/2020 MANUEL GARCIA
Quality Review Completed 1/31/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/4/2020 APPLICANT
Plan Check Approved 2/14/2020 MANUEL GARCIA
Issued 3/11/2020 LADBS
CofO in Progress 1/25/2021 HENRY KIM
CofO Issued 1/26/2021 JOHN JANSON
Permit Finaled 1/26/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/10/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 2/10/2020 CHINH DINH
Sewer availability Cleared 2/10/2020 CHINH DINH
Green Code Cleared 2/11/2020 MANUEL GARCIA

Contact Information

Architect Puskar,, Heidi M; Lic. No.: C28223 29431 N ENROSE AVENUE      RANCHO PALOS VERDES, CA 90275
Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/7/2020 Corrections Issued HENRY KIM
Footing/Foundation/Slab 7/15/2020 Approved HENRY KIM
PLUMBING-Rough 7/15/2020 Partial Approval HENRY KIM
Sewer 7/15/2020 Approved HENRY KIM
PLUMBING-Rough 7/22/2020 Partial Approval HENRY KIM
Underground Mechanical 7/22/2020 Partial Approval HENRY KIM
Insulation 8/3/2020 Partial Approval HENRY KIM
ELECTRICAL-Rough 8/13/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 8/17/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/17/2020 Approved HENRY KIM
Green Building Rough 8/17/2020 Approved HENRY KIM
Insulation 8/17/2020 Partial Approval HENRY KIM
PLUMBING-Rough 8/17/2020 Approved HENRY KIM
Drywall Nailing 8/24/2020 Approved HENRY KIM
Insulation 8/24/2020 Approved HENRY KIM
Interior/Exterior Lathing 8/24/2020 Approved HENRY KIM
Special/Order Compliance 8/24/2020 Approved HENRY KIM
Interior/Exterior Lathing 9/22/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 11/17/2020 Corrections Issued HENRY KIM
Final 11/17/2020 Corrections Issued HENRY KIM
Green Building Final 11/17/2020 Approved HENRY KIM
HVAC-Final 11/17/2020 Corrections Issued HENRY KIM
PLUMBING-Final 11/17/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Not Ready HENRY KIM
Smoke Detectors 11/17/2020 Approved HENRY KIM
ELECTRICAL-Final 11/25/2020 Corrections Issued HENRY KIM
Final 11/25/2020 Corrections Issued HENRY KIM
HVAC-Final 11/25/2020 Corrections Issued HENRY KIM
PLUMBING-Final 11/25/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Not Ready HENRY KIM
ELECTRICAL-Final 12/10/2020 Approved HENRY KIM
Final 12/10/2020 Corrections Issued HENRY KIM
HVAC-Final 12/10/2020 Approved HENRY KIM
PLUMBING-Final 12/10/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Approved HENRY KIM
Service/Power Release 12/10/2020 Not Ready for Inspection HENRY KIM
Final 1/25/2021 OK to Issue CofO HENRY KIM
Service/Power Release 1/25/2021 Approved HENRY KIM