910 S OLIVE ST 90015

Certificate Information: 910 S OLIVE ST 90015

Application / Permit
19016-40000-38734
Plan Check / Job No.
B19SP01847
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Change of use and combine existing two retail tenants into one office use tenant.
Permit Issued
Issued on 1/8/2021
Issuing Office
Current Status
CofO Issued on 12/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 12/23/2019 APPLICANT
Corrections Issued 12/24/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/10/2020 TARIK SAOUD
Disabled Access Plans Picked Up 1/10/2020 APPLICANT
Plan Check Approved 7/1/2020 VLADIMIR ARUTYUNYAN
Issued 1/8/2021 APPLICANT
Building Plans Picked Up 1/13/2021 APPLICANT
CofO in Progress 12/29/2022 ERNESTO CORRAL
Permit Finaled 12/29/2022 ERNESTO CORRAL
CofO Issued 12/29/2022 ERNESTO CORRAL
Permit Finaled 12/29/2022 ERNESTO CORRAL

Permit Application Clearance Information

"D" conditions Cleared 1/15/2020 TERRI OSBORNE
"Q" conditions Cleared 1/15/2020 TERRI OSBORNE
Address approval Cleared 1/15/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/15/2020 ERIK BEASLEY
Sewer availability Cleared 1/15/2020 ERIK BEASLEY
Historic Resource Verification Cleared 1/24/2020 GISELLE CORELLA
Redevelopment Project Area Cleared 1/24/2020 GISELLE CORELLA
Green Code Cleared 2/13/2020 DONALD CRICHLOW
DAS Clearance Cleared 2/25/2020 SOMKIAT SUPANYACHOTSKUL
ZA Case Cleared 5/21/2020 NOAH MCCOY

Contact Information

Contractor Bluestone Construction Corp; Lic. No.: 952370-B 6520 PLATT AVENUE #805      WEST HILLS, CA 91307
Engineer Melnyk,, Matthew John; Lic. No.: S5853 527 WEST 7TH ST STE 701      LOS ANGELES, CA 90014

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/11/2021 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/26/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 5/27/2021 Partial Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 6/9/2021 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/18/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 7/20/2021 Partial Inspection DANIEL COLLINS
Deputy Reinf. Concrete 7/21/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 7/28/2021 Conditional Approval DANIEL COLLINS
Deputy Wood Construction 8/12/2021 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 8/25/2021 Approved DANIEL COLLINS
Insulation 8/25/2021 Approved DANIEL COLLINS
Deputy Drilled-In Anchors 9/7/2021 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 9/13/2021 Conditional Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 9/28/2021 Approved TIMOTHY BUXTON
Wood Frame 9/28/2021 Approved TIMOTHY BUXTON
Drywall Nailing 10/5/2021 Partial Approval TIMOTHY BUXTON
Drywall Nailing 2/1/2022 Not Ready for Inspection TIMOTHY BUXTON
Drywall Nailing 2/2/2022 Approved JONATHAN QUACH
Drywall Nailing 2/15/2022 Partial Approval TIMOTHY BUXTON
Drywall Nailing 2/24/2022 Approved TIMOTHY BUXTON
Final 8/11/2022 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 8/11/2022 Not Ready for Inspection TIMOTHY BUXTON
METHANE-Final 8/11/2022 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved TIMOTHY BUXTON
Smoke Detectors 8/11/2022 Approved TIMOTHY BUXTON
Final 10/11/2022 Not Ready for Inspection TIMOTHY BUXTON
Green Building Final 10/11/2022 Not Ready for Inspection TIMOTHY BUXTON
Final 12/19/2022 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 12/19/2022 Not Ready for Inspection RAMAZANALI ALMASI
Final 12/27/2022 Partial Approval RAMAZANALI ALMASI
Green Building Final 12/27/2022 Approved RAMAZANALI ALMASI
Final 12/29/2022 OK to Issue CofO ERNESTO CORRAL