1507 W 82ND ST 90047

Certificate Information: 1507 W 82ND ST 90047

Application / Permit
19016-40000-37932
Plan Check / Job No.
B19SP01817
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior/Exterior alteration to (E) one-story Single Family dwelling to extend portion of (E) living room by converting portion (98 SF) of (E) covered patio to living space. Scope of work to include replacing posts of front patio. All work per engineered design.
Permit Issued
Issued on 3/5/2020
Issuing Office
San Pedro
Current Status
CofO Issued on 9/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2019 APPLICANT
Assigned to Plan Check Engineer 11/25/2019 LAMAR DAVIS
Corrections Issued 11/25/2019 LAMAR DAVIS
Plan Check Approved 2/7/2020 JASON JANGADA
Issued 3/5/2020 LADBS
CofO in Progress 8/27/2021 JOAQUIN GREENOUGH
Permit Finaled 9/3/2021 DEROLD HAUFF
CofO Issued 9/3/2021 DEROLD HAUFF
Permit Finaled 9/3/2021 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Pelayo,, Victor; Lic. No.: C73094 736 N 4TH STREET      MONTEBELLO, CA 90640

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/19/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/24/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 4/10/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 4/10/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/22/2020 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 4/22/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/22/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 4/22/2020 Approved EUGENE CASSIDY
Green Building Rough 4/22/2020 Approved EUGENE CASSIDY
Insulation 4/22/2020 Approved EUGENE CASSIDY
Drywall Nailing 5/27/2020 Not Ready for Inspection BRIAN CHRISTIAN
Interior/Exterior Lathing 5/27/2020 Not Ready for Inspection BRIAN CHRISTIAN
Drywall Nailing 8/12/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/12/2020 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 4/27/2021 Approved EUGENE CASSIDY
Final 4/27/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 4/27/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/27/2021 Corrections Issued EUGENE CASSIDY
Final 7/29/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 7/29/2021 Not Ready for Inspection FREDDIE RIVERA
Smoke Detectors 7/29/2021 Conditional Approval FREDDIE RIVERA
Final 8/5/2021 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 8/5/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 8/5/2021 Corrections Issued JOAQUIN GREENOUGH
Final 8/26/2021 OK to Issue CofO JOAQUIN GREENOUGH
Green Building Final 8/26/2021 Approved JOAQUIN GREENOUGH
Smoke Detectors 8/26/2021 Approved JOAQUIN GREENOUGH