750 W BASIN ST 90731
Certificate Information: 750 W BASIN ST 90731
- Application / Permit
- 19016-40000-35407
- Plan Check / Job No.
- B19SP01699
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Bakery
- Work Description
- Interior and Exterior core-and-shell alteration to (E) one-story bakery building. Scope of work to include opening in (E) tilt-up wall to provide (N) vehicle access ramp at (E) South elevation and installation of accessible entry ramp. All work per engineered plans.
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 5/18/2020
Permit Application Status History
| Submitted | 11/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | MANUEL GARCIA |
| Disabled Access Plans Picked Up | 11/15/2019 | APPLICANT |
| Corrections Issued | 11/18/2019 | MANUEL GARCIA |
| Quality Review Completed | 11/27/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/9/2019 | APPLICANT |
| Plan Check Approved | 1/10/2020 | MANUEL GARCIA |
| Issued | 2/4/2020 | LADBS |
| Permit Finaled | 5/18/2020 | JOEY BUCHANAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/17/2019 | SHINE LIN |
| "D" conditions | Cleared | 1/3/2020 | JEANALEE OBERGFELL |
| Community Plan Implem. Overlay | Cleared | 1/3/2020 | JEANALEE OBERGFELL |
Contact Information
| Architect | Ottolia,, Domingo C; Lic. No.: C27790 | 5533 BAYRIDGE RD. RANCHO PALOS VERDES, CA 90275 |
| Contractor | Simich John Construction Inc; Lic. No.: 410855-B | 1400 S HARBOR BLVD SAN PEDRO, CA 90731 |
| Engineer | Bell,, William Andrew; Lic. No.: C88870 | 22403 LADEENE AVE TORRANCE, CA 90505 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 3/16/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 3/16/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 4/20/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/20/2020 | Partial Approval | JOEY BUCHANAN |
| Final | 5/18/2020 | Permit Finaled | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2020 | SGSOV No Gas | JOEY BUCHANAN |
| Smoke Detectors | 5/18/2020 | Approved | JOEY BUCHANAN |