802 E ANAHEIM ST 90744

Certificate Information: 802 E ANAHEIM ST 90744

Application / Permit
19016-40000-22847
Plan Check / Job No.
B19SP01160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Adhesive Manufacturing liquid
Work Description
Change of use of (E) 1-story warehouse/office building to liquid adhesive manufacturing building. Restripe/re-arrange portion of parking. New storage rack anchorage and equipment foundation and anchorage.
Permit Issued
Issued on 7/6/2020
Issuing Office
Current Status
CofO Issued on 8/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 RODOLFO ARIAS
Corrections Issued 8/12/2019 RODOLFO ARIAS
Quality Review Completed 8/12/2019 GARO TELMI
Building Plans Picked Up 8/14/2019 APPLICANT
Disabled Access Plans Picked Up 8/14/2019 APPLICANT
Green Plans Picked Up 8/14/2019 APPLICANT
Applicant returned to address corrections 10/7/2019 RODOLFO ARIAS
Applicant returned to address corrections 10/11/2019 RODOLFO ARIAS
Applicant returned to address corrections 11/14/2019 RODOLFO ARIAS
Applicant returned to address corrections 12/5/2019 RODOLFO ARIAS
Applicant returned to address corrections 5/8/2020 RODOLFO ARIAS
Applicant returned to address corrections 5/15/2020 RODOLFO ARIAS
Plan Check Approved 6/19/2020 RODOLFO ARIAS
Issued 7/6/2020 APPLICANT
CofO in Progress 7/15/2022 JOEY BUCHANAN
Permit Finaled 8/10/2022 DAVID TSAU
CofO Issued 8/10/2022 DAVID TSAU
Permit Finaled 8/10/2022 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 10/3/2019 SARAHI ORTEGA
Address approval Cleared 10/3/2019 EMIL KYUPELYAN
CPC Cleared 10/3/2019 SARAHI ORTEGA
Project located in CRA area Cleared 10/3/2019 JIM URQUHART
ZA Case Cleared 11/5/2019 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 11/15/2019 CELINA MORENO
Clean Up Green Up Cleared 11/20/2019 RICHARD REASER
DAS Clearance Cleared 11/21/2019 WAI LAU
Prkng lot landscape/Water mgmt Cleared 12/10/2019 RICHARD REASER
Green Code Cleared 12/19/2019 DONALD CRICHLOW
Abandoned oil well Cleared 5/1/2020 GEORGE SUCHAND
Sewer availability Cleared 6/2/2020 CHINH DINH

Contact Information

Architect Kamps,, Curtis J; Lic. No.: C25872 18 SWEET RAIN      IRVINE, CA 92614
Contractor C R M Construction Incorporated; Lic. No.: 310970-B 296 GLENDORA AVE      LONG BEACH, CA 90803
Engineer Yaghi,, Shucri Ibrahim; Lic. No.: C43205 112 E CHAPMAN AVE STE D      ORANGE, CA 92866

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/8/2020 Corrections Issued JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 7/20/2020 Approved JOEY BUCHANAN
Light Gage Steel Frame 7/20/2020 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 7/21/2020 Approved JOEY BUCHANAN
Drywall Nailing 7/24/2020 Approved JOEY BUCHANAN
Drywall Nailing 7/27/2020 Approved JOEY BUCHANAN
Wood Frame 8/5/2020 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 9/18/2020 Approved JOEY BUCHANAN
Final 11/9/2021 Corrections Issued JOEY BUCHANAN
Green Building Final 11/9/2021 Approved JOEY BUCHANAN
Green Building Rough 11/9/2021 Approved JOEY BUCHANAN
METHANE-Final 11/9/2021 Approved JOEY BUCHANAN
METHANE-Rough 11/9/2021 Approved JOEY BUCHANAN
Reinforced Masonry Frame 11/9/2021 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 11/9/2021 SGSOV No Gas JOEY BUCHANAN
Smoke Detectors 11/9/2021 Approved JOEY BUCHANAN
Final 3/9/2022 Not Ready for Inspection JOEY BUCHANAN
Final 7/14/2022 Conditional Approval JOEY BUCHANAN