11540 W COOLIDGE PL 90066

Certificate Information: 11540 W COOLIDGE PL 90066

Application / Permit
19016-30001-40893
Plan Check / Job No.
B20WL02532
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental to 19016-30000-40893 to revise structural framing based on as-built conditions to (E) SFD and change engineer of record.
Permit Issued
Issued on 8/20/2020
Issuing Office
Current Status
CofO Issued on 2/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 ALFREDO JARA
Corrections Issued 6/19/2020 ALFREDO JARA
Applicant returned to address corrections 7/9/2020 ALFREDO JARA
Applicant returned to address corrections 7/13/2020 ALFREDO JARA
Applicant returned to address corrections 7/22/2020 JASON JANGADA
Applicant returned to address corrections 7/30/2020 JASON JANGADA
Plan Check Approved 8/7/2020 PARISA ZAHABI
Issued 8/20/2020 APPLICANT
Building Plans Picked Up 8/21/2020 APPLICANT
CofO in Progress 2/11/2023 DAVID FEILER
Permit Finaled 2/13/2023 DANIEL ORRANTE
CofO Issued 2/13/2023 DANIEL ORRANTE
Permit Finaled 2/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Schevers Construction; Lic. No.: 802078-B 7731 BOEING AVENUE      LOS ANGELES, CA 90045
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 8/24/2020 Partial Approval EVAN COOPER
HVAC-Rough 8/24/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 8/24/2020 Partial Approval EVAN COOPER
Special/Order Compliance 12/23/2020 Not Ready for Inspection RICHARD ROBLES
BUILDING-Rough-Frame 2/10/2021 Approved RICHARD ROBLES
Drywall Nailing 2/10/2021 Approved RICHARD ROBLES
Final 2/10/2021 OK to Issue CofO RICHARD ROBLES
Footing/Foundation/Slab 2/10/2021 Approved RICHARD ROBLES
Green Building Final 2/10/2021 Approved RICHARD ROBLES
Green Building Rough 2/10/2021 Approved RICHARD ROBLES
Smoke Detectors 2/10/2021 Approved RICHARD ROBLES