15 E ROSE AVE 1-25 90291
Certificate Information: 15 E ROSE AVE 1-25 90291
- Application / Permit
- 19016-30001-30552
- Plan Check / Job No.
- B20WL01738
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment Hotel
- Work Description
- Supplemental to 19016-30000-30552 to include remodeling 14 light-housekeeping rooms. No (n) area & no (n) exterior work.
- Permit Issued
- Issued on 9/11/2020
- Issuing Office
- Current Status
- Permit Finaled on 12/12/2022
Permit Application Status History
| Submitted | 4/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | KAVIAN REFAHI |
| Corrections Issued | 5/11/2020 | KAVIAN REFAHI |
| Quality Review Completed | 5/18/2020 | TARIK SAOUD |
| Green Plans Picked Up | 7/13/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 8/26/2020 | APPLICANT |
| Plan Check Approved | 9/1/2020 | KAVIAN REFAHI |
| Issued | 9/11/2020 | APPLICANT |
| Building Plans Picked Up | 9/16/2020 | APPLICANT |
| Permit Finaled | 12/12/2022 | SORIN CIRSTOIU |
Permit Application Clearance Information
| Green Code | Cleared | 7/10/2020 | RICHARD GARCIA |
| DAS Clearance | Cleared | 7/30/2020 | SOMKIAT SUPANYACHOTSKUL |
| Fire Marshall Fire Life Safety | Cleared | 8/18/2020 | VIDAL GARCIA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | J C A Construction Company; Lic. No.: 940685-B | 8665 WILSHIRE BLVD #410 BEVERLY HILLS, CA 90211 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 11/30/2020 | Partial Inspection | SORIN CIRSTOIU |
| Insulation | 12/8/2020 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 4/21/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 4/26/2021 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 4/26/2021 | Not Ready for Inspection | JOHN DODGE |
| Drywall Nailing | 4/29/2021 | Partial Approval | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 4/29/2021 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 4/29/2021 | Partial Inspection | SORIN CIRSTOIU |
| Drywall Nailing | 5/4/2021 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 5/4/2021 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 5/4/2021 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 5/12/2021 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 5/13/2021 | Partial Approval | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 5/13/2021 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 5/14/2021 | Partial Inspection | SORIN CIRSTOIU |
| Insulation | 5/14/2021 | Partial Inspection | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 5/14/2021 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 5/14/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Drywall Nailing | 5/18/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Insulation | 5/18/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 5/18/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 5/18/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Drywall Nailing | 5/19/2021 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 5/19/2021 | Partial Inspection | SORIN CIRSTOIU |
| Interior/Exterior Lathing | 5/19/2021 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 5/19/2021 | Approved | SORIN CIRSTOIU |
| Insulation | 5/24/2021 | Approved | SORIN CIRSTOIU |
| Drywall Nailing | 6/3/2021 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 6/17/2021 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 7/8/2021 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 9/1/2021 | Approved | SORIN CIRSTOIU |
| Final | 12/12/2022 | Permit Finaled | SORIN CIRSTOIU |
| Green Building Final | 12/12/2022 | Approved | SORIN CIRSTOIU |
| Smoke Detectors | 12/12/2022 | Approved | SORIN CIRSTOIU |