6516 W 87TH ST 90045
Certificate Information: 6516 W 87TH ST 90045
- Application / Permit
- 19016-30000-41380
- Plan Check / Job No.
- B19WL07385
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to ADU.
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 1/9/2020 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 1/15/2020 | APPLICANT |
| Plan Check Approved | 3/18/2020 | PARISA ZAHABI |
| Plan Check Approved | 3/18/2020 | DAISY GUILLEN |
| Issued | 3/18/2020 | LADBS |
| CofO in Progress | 2/25/2021 | DAVID HEINE |
| CofO in Progress | 4/26/2021 | BRENDAN LOONEY |
| Permit Finaled | 6/4/2021 | RONALD MYRICK |
| CofO Issued | 6/4/2021 | RONALD MYRICK |
| Permit Finaled | 6/4/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2020 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/27/2020 | APEKSHYA BAJRACHARYA |
| Construction near power lines | Cleared | 3/12/2020 | TORI CHEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/18/2020 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/20/2020 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 11/20/2020 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 11/25/2020 | Approved | JUAN VALENZUELA |
| Sewer | 11/25/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/1/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/1/2020 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 12/1/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/1/2020 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 12/1/2020 | Approved | JUAN VALENZUELA |
| Insulation | 12/3/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/3/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 12/4/2020 | Approved | DAVID HEINE |
| Final | 2/10/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 2/10/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 2/10/2021 | Approved | JOHNNY MIRANDA |
| Final | 2/16/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 2/16/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 2/25/2021 | Approved | DAVID HEINE |
| Final | 2/25/2021 | OK to Issue CofO | DAVID HEINE |
| HVAC-Final | 2/25/2021 | Approved | DAVID HEINE |
| PLUMBING-Final | 2/25/2021 | Approved | DAVID HEINE |
| Special/Order Compliance | 3/9/2021 | No Access for Inspection | DAVID HEINE |
| Final | 4/22/2021 | OK to Issue CofO | BRENDAN LOONEY |