1217 E ELM ST 90291
Certificate Information: 1217 E ELM ST 90291
- Application / Permit
- 19016-30000-41312
- Plan Check / Job No.
- B19WL07364
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior / exterior alteration to (e) SFD, enclose portion of (e) covered porch to enlarge living room(42 sf) (3'-6" x 12'-0").
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 9/17/2020
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2019 | REZA HAGHIGHAT |
| Corrections Issued | 12/30/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 2/7/2020 | JAHANSHAH POURHASSAN |
| Issued | 2/14/2020 | LADBS |
| Permit Finaled | 9/16/2020 | CRAIG DAVIS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Park,, Sang Hun; Lic. No.: C33387 | 1424 4TH ST. #700B SANTA MONICA, CA 90401 |
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 3/9/2020 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 3/9/2020 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 3/9/2020 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 3/9/2020 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/9/2020 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/19/2020 | Approved | DAVID FEILER |
| PLUMBING-Rough | 3/27/2020 | Partial Approval | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 5/11/2020 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 5/11/2020 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 5/28/2020 | Approved | DAVID FEILER |
| HVAC-Rough | 5/28/2020 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/5/2020 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | CRAIG DAVIS |
| Insulation | 6/9/2020 | Approved | CRAIG DAVIS |
| Drywall Nailing | 6/15/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/15/2020 | Approved | EVAN COOPER |
| Shower Pan | 6/15/2020 | Approved | EVAN COOPER |
| Final | 8/17/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 8/17/2020 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/17/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 8/17/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/21/2020 | Approved | CRAIG DAVIS |
| HVAC-Final | 8/21/2020 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 8/21/2020 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 9/3/2020 | Partial Approval | CRAIG DAVIS |
| Green Building Final | 9/3/2020 | Approved | CRAIG DAVIS |
| Green Building Rough | 9/3/2020 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/3/2020 | Approved | CRAIG DAVIS |
| Final | 9/4/2020 | Partial Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/4/2020 | SGSOV Approved | CRAIG DAVIS |
| Final | 9/16/2020 | Permit Finaled | CRAIG DAVIS |
| Service/Power Release | 9/16/2020 | Approved | CRAIG DAVIS |