10429 W TROON AVE 90064
Certificate Information: 10429 W TROON AVE 90064
- Application / Permit
- 19016-30000-41283
- Plan Check / Job No.
- B19WL07356
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) garage to accessory dwelling unit. Per AB 494 & SB229. Per engineering design.
- Permit Issued
- Issued on 6/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | ALFREDO JARA |
| Corrections Issued | 1/3/2020 | ALFREDO JARA |
| Applicant returned to address corrections | 6/30/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 7/22/2022 | JASON JANGADA |
| Plan Check Approved | 8/17/2022 | ALFREDO JARA |
| Building Plans Picked Up | 8/25/2022 | APPLICANT |
| Issued | 6/12/2023 | APPLICANT |
| Permit Finaled | 12/18/2025 | RICHARD STEINBACH |
| CofO Issued | 12/18/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/18/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 2/4/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/4/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 6/30/2022 | ALFREDO JARA |
| ZA Case | Cleared | 8/3/2022 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 8/9/2022 | FREDDY GARCIA |
Contact Information
| Contractor | Yd Construction & Development Inc; Lic. No.: 839200-B | 15030 VENTURA BLVD #216 SHERMAN OAKS, CA 91403 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 6/17/2024 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 6/27/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Barrier | 7/1/2024 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 7/1/2024 | Partial Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 7/3/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/24/2024 | Approved | ASHLEY THOMPSON |
| METHANE-Barrier | 7/24/2024 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/11/2024 | Conditional Approval | ASHLEY THOMPSON |
| Underground Mechanical | 10/11/2024 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 10/22/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 10/22/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 10/22/2024 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Rough | 10/22/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/11/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 2/11/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Rough | 2/11/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/11/2025 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/27/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 3/27/2025 | Conditional Approval | ARAM AVEDISIAN |
| METHANE-Rough | 3/27/2025 | Approved | ARAM AVEDISIAN |
| Shower Pan | 3/27/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 4/11/2025 | Approved | ARAM AVEDISIAN |
| Insulation | 4/11/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 4/29/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/23/2025 | Corrections Issued | ASHLEY THOMPSON |
| Final | 10/23/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 10/23/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 10/23/2025 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Not Required | ASHLEY THOMPSON |
| Smoke Detectors | 10/23/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/2/2025 | Approved | ASHLEY THOMPSON |
| Final | 12/2/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 12/2/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 12/2/2025 | Approved | ASHLEY THOMPSON |
| Final | 12/12/2025 | Conditional Approval | ASHLEY THOMPSON |