5183 W SANCHEZ DR 90008
Certificate Information: 5183 W SANCHEZ DR 90008
- Application / Permit
- 19016-30000-40908
- Plan Check / Job No.
- B19WL07252
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of (e) att. 2-car garage to an accessory dwelling unit (ADU) per AB 68 (379sqft). All work per IB/P/BC 2017-004 wood frame prescriptive provision.
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/24/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | TARIK SAOUD |
| Corrections Issued | 1/1/2020 | TARIK SAOUD |
| Building Plans Picked Up | 1/7/2020 | APPLICANT |
| Plan Check Approved | 1/16/2020 | REZA HAGHIGHAT |
| Issued | 1/24/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 1/16/2020 | JUAN ASHTON |
| CPC | Cleared | 1/16/2020 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | JUAN ASHTON |
| Grading Pre-Inspection | Cleared | 1/16/2020 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 1/16/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 1/16/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/11/2020 | Partial Approval | COREY HUPP |
| Deputy Drilled-In Anchors | 2/13/2020 | Conditional Approval | COREY HUPP |
| Footing/Foundation/Slab | 2/14/2020 | Approved | COREY HUPP |
| Insulation | 2/19/2020 | Partial Approval | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 4/1/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 4/6/2020 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/10/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/10/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/10/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/10/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/14/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/17/2020 | Corrections Issued | SABAS ALONSO |
| Final | 5/11/2020 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 5/11/2020 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 5/11/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 5/18/2020 | Conditional Approval | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 5/18/2020 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 5/18/2020 | Approved | COREY HUPP |