5183 W SANCHEZ DR 90008

Certificate Information: 5183 W SANCHEZ DR 90008

Application / Permit
19016-30000-40908
Plan Check / Job No.
B19WL07252
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Conversion of (e) att. 2-car garage to an accessory dwelling unit (ADU) per AB 68 (379sqft). All work per IB/P/BC 2017-004 wood frame prescriptive provision.
Permit Issued
Issued on 1/24/2020
Issuing Office
West Los Angeles
Current Status
Issued on 1/24/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 12/31/2019 TARIK SAOUD
Corrections Issued 1/1/2020 TARIK SAOUD
Building Plans Picked Up 1/7/2020 APPLICANT
Plan Check Approved 1/16/2020 REZA HAGHIGHAT
Issued 1/24/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 1/16/2020 JUAN ASHTON
CPC Cleared 1/16/2020 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 1/16/2020 JUAN ASHTON
Grading Pre-Inspection Cleared 1/16/2020 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 1/16/2020 JUAN ASHTON
Sewer availability Cleared 1/16/2020 JUAN ASHTON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/11/2020 Partial Approval COREY HUPP
Deputy Drilled-In Anchors 2/13/2020 Conditional Approval COREY HUPP
Footing/Foundation/Slab 2/14/2020 Approved COREY HUPP
Insulation 2/19/2020 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 4/1/2020 Approved COREY HUPP
BUILDING-Rough-Frame 4/6/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 4/10/2020 Approved CHRISTOPHER DELLEFIELD
Insulation 4/10/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/10/2020 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 4/10/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 4/14/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 4/17/2020 Corrections Issued SABAS ALONSO
Final 5/11/2020 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/11/2020 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 5/11/2020 Not Ready for Inspection ENRIQUE MIRELES
Final 5/18/2020 Conditional Approval COREY HUPP
SGSOV-Seismic Gas S/O Valve 5/18/2020 SGSOV Approved COREY HUPP
Smoke Detectors 5/18/2020 Approved COREY HUPP