541 E ROSE AVE 90291
Certificate Information: 541 E ROSE AVE 90291
- Application / Permit
- 19016-30000-40681
- Plan Check / Job No.
- B19WL07145
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Alteration to existing 1-story Duplex. NFPA-13D Sprinkler is required.
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 10/7/2020
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2019 | MANUEL GARCIA |
| Corrections Issued | 12/27/2019 | MANUEL GARCIA |
| Building Plans Picked Up | 12/31/2019 | APPLICANT |
| Applicant returned to address corrections | 2/10/2020 | PARISA ZAHABI |
| Plan Check Approved | 2/10/2020 | PARISA ZAHABI |
| Issued | 2/14/2020 | LADBS |
| Permit Finaled | 10/7/2020 | DAVID HEINE |
Permit Application Clearance Information
| Address approval | Cleared | 2/7/2020 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 2/7/2020 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | ANTHONY MAINEZ |
| Frnt yard landscape/Water mgmt | Cleared | 2/7/2020 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 2/7/2020 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 2/7/2020 | DENZEL HENDERSON |
| Sewer availability | Cleared | 2/7/2020 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 2/7/2020 | IRA BROWN |
| Tenant Habitability Plan | Cleared | 2/7/2020 | PHILLIP MUNGUIA |
| ZA Case | Cleared | 2/7/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 2/7/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 2/7/2020 | DENZEL HENDERSON |
Contact Information
| Contractor | Waconah Construction; Lic. No.: 908219-B | 2431 1/2 ABBOT KINNEY BLVD VENICE, CA 90291 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/4/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 3/13/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 4/29/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 5/1/2020 | Corrections Issued | DAVID HEINE |
| HVAC-Rough | 5/1/2020 | Corrections Issued | DAVID HEINE |
| ELECTRICAL-Rough | 5/8/2020 | Approved | DAVID HEINE |
| Shower Pan | 5/8/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 5/12/2020 | Partial Approval | DAVID HEINE |
| HVAC-Rough | 5/12/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 5/14/2020 | Partial Approval | DAVID HEINE |
| Insulation | 5/19/2020 | Approved | DAVID HEINE |
| Underground Mechanical | 5/19/2020 | Partial Approval | DAVID HEINE |
| Interior/Exterior Lathing | 5/22/2020 | Partial Approval | DAVID HEINE |
| Drywall Nailing | 6/5/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 7/21/2020 | Approved | DAVID HEINE |
| Service/Power Release | 7/21/2020 | Approved | DAVID HEINE |
| Gas Test | 7/28/2020 | Approved | DAVID HEINE |
| Final | 9/9/2020 | Corrections Issued | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 9/9/2020 | SGSOV Not Ready | DAVID HEINE |
| Smoke Detectors | 9/9/2020 | Approved | DAVID HEINE |
| Final | 9/16/2020 | Not Ready for Inspection | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 9/16/2020 | SGSOV Not Ready | DAVID HEINE |
| Service/Power Release | 9/16/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 9/17/2020 | Approved | DAVID HEINE |
| PLUMBING-Final | 9/17/2020 | Approved | DAVID HEINE |
| Final | 9/23/2020 | Corrections Issued | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 9/23/2020 | SGSOV Approved | DAVID HEINE |
| PLUMBING-Final | 9/25/2020 | Approved | DAVID HEINE |
| Final | 10/1/2020 | Conditional Approval | DAVID HEINE |
| Final | 10/7/2020 | Permit Finaled | DAVID HEINE |