541 E ROSE AVE 90291

Certificate Information: 541 E ROSE AVE 90291

Application / Permit
19016-30000-40681
Plan Check / Job No.
B19WL07145
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Alteration to existing 1-story Duplex. NFPA-13D Sprinkler is required.
Permit Issued
Issued on 2/14/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 10/7/2020

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 12/23/2019 MANUEL GARCIA
Corrections Issued 12/27/2019 MANUEL GARCIA
Building Plans Picked Up 12/31/2019 APPLICANT
Applicant returned to address corrections 2/10/2020 PARISA ZAHABI
Plan Check Approved 2/10/2020 PARISA ZAHABI
Issued 2/14/2020 LADBS
Permit Finaled 10/7/2020 DAVID HEINE

Permit Application Clearance Information

Address approval Cleared 2/7/2020 ANTHONY MAINEZ
Coastal Zone Cleared 2/7/2020 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 2/7/2020 ANTHONY MAINEZ
Frnt yard landscape/Water mgmt Cleared 2/7/2020 DENZEL HENDERSON
Miscellaneous Cleared 2/7/2020 DENZEL HENDERSON
Miscellaneous Cleared 2/7/2020 DENZEL HENDERSON
Sewer availability Cleared 2/7/2020 ANTHONY MAINEZ
Specific Plan Cleared 2/7/2020 IRA BROWN
Tenant Habitability Plan Cleared 2/7/2020 PHILLIP MUNGUIA
ZA Case Cleared 2/7/2020 DENZEL HENDERSON
ZA Case Cleared 2/7/2020 DENZEL HENDERSON
ZA Case Cleared 2/7/2020 DENZEL HENDERSON

Contact Information

Contractor Waconah Construction; Lic. No.: 908219-B 2431 1/2 ABBOT KINNEY BLVD      VENICE, CA 90291

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 3/13/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 4/29/2020 Approved DAVID HEINE
ELECTRICAL-Rough 5/1/2020 Corrections Issued DAVID HEINE
HVAC-Rough 5/1/2020 Corrections Issued DAVID HEINE
ELECTRICAL-Rough 5/8/2020 Approved DAVID HEINE
Shower Pan 5/8/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 5/12/2020 Partial Approval DAVID HEINE
HVAC-Rough 5/12/2020 Approved DAVID HEINE
Interior/Exterior Lathing 5/14/2020 Partial Approval DAVID HEINE
Insulation 5/19/2020 Approved DAVID HEINE
Underground Mechanical 5/19/2020 Partial Approval DAVID HEINE
Interior/Exterior Lathing 5/22/2020 Partial Approval DAVID HEINE
Drywall Nailing 6/5/2020 Approved DAVID HEINE
ELECTRICAL-Final 7/21/2020 Approved DAVID HEINE
Service/Power Release 7/21/2020 Approved DAVID HEINE
Gas Test 7/28/2020 Approved DAVID HEINE
Final 9/9/2020 Corrections Issued DAVID HEINE
SGSOV-Seismic Gas S/O Valve 9/9/2020 SGSOV Not Ready DAVID HEINE
Smoke Detectors 9/9/2020 Approved DAVID HEINE
Final 9/16/2020 Not Ready for Inspection DAVID HEINE
SGSOV-Seismic Gas S/O Valve 9/16/2020 SGSOV Not Ready DAVID HEINE
Service/Power Release 9/16/2020 Approved DAVID HEINE
ELECTRICAL-Final 9/17/2020 Approved DAVID HEINE
PLUMBING-Final 9/17/2020 Approved DAVID HEINE
Final 9/23/2020 Corrections Issued DAVID HEINE
SGSOV-Seismic Gas S/O Valve 9/23/2020 SGSOV Approved DAVID HEINE
PLUMBING-Final 9/25/2020 Approved DAVID HEINE
Final 10/1/2020 Conditional Approval DAVID HEINE
Final 10/7/2020 Permit Finaled DAVID HEINE