3374 S MCLAUGHLIN AVE 90066
Certificate Information: 3374 S MCLAUGHLIN AVE 90066
- Application / Permit
- 19016-30000-40544
- Plan Check / Job No.
- B19WL07118
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) 439 SF GARAGE & POOL HOUSE TO AN ADU. (N) FIXTURES AND FINISHES THROUGHOUT.
- Permit Issued
- Issued on 3/20/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Building Plans Picked Up | 1/10/2019 | APPLICANT |
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2019 | JAHANSHAH POURHASSAN |
| Corrections Issued | 1/6/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 3/19/2020 | PARISA ZAHABI |
| Issued | 3/20/2020 | LADBS |
| CofO in Progress | 4/8/2021 | EVAN COOPER |
| No Progress | 4/23/2021 | KENNETH NAGLE |
| CofO in Progress | 6/9/2021 | KENNETH NAGLE |
| Permit Finaled | 6/9/2021 | KENNETH NAGLE |
| CofO Issued | 6/9/2021 | KENNETH NAGLE |
| Permit Finaled | 6/9/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 1/10/2020 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/10/2020 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 1/23/2020 | BRIAN OLSON |
| Hydrant and Access approval | Cleared | 1/23/2020 | DOMINIQUE MEDINA |
Contact Information
| Architect | Marsh,, Michael Hirst; Lic. No.: C37669 | 11629 NATIONAL BLVD #3 LOS ANGELES, CA 90064 |
| Contractor | Whitaker Construction; Lic. No.: 804990-B | 29595 PUJOL ST #10314 TEMECULA, CA 92590 |
| Engineer | Mezey,, Steven William; Lic. No.: S2665 | 14017 HARTSOOK ST SHERMAN OAKS, CA 91423 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2020 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 5/29/2020 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 6/8/2020 | Corrections Issued | DAVID FEILER |
| Wood Frame | 6/19/2020 | Conditional Approval | JUSTIN CURTIS |
| Insulation | 6/29/2020 | Corrections Issued | JUSTIN CURTIS |
| Insulation | 7/8/2020 | Approved | JUSTIN CURTIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2020 | Conditional Approval | JUSTIN CURTIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2020 | Approved | JUSTIN CURTIS |
| Drywall Nailing | 10/20/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/26/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/28/2020 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 11/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Special/Order Compliance | 11/2/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 1/25/2021 | No Access for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/25/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 1/25/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Wood Frame | 1/25/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Final | 1/28/2021 | Corrections Issued | RICHARD ROBLES |
| SGSOV-Seismic Gas S/O Valve | 1/28/2021 | SGSOV Not Ready | RICHARD ROBLES |
| Smoke Detectors | 1/28/2021 | Corrections Issued | RICHARD ROBLES |
| Wood Frame | 1/28/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Final | 3/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 3/18/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 4/7/2021 | Conditional Approval | EVAN COOPER |
| Smoke Detectors | 4/7/2021 | Approved | EVAN COOPER |
| Special/Order Compliance | 4/8/2021 | Corrections Issued | EVAN COOPER |