2122 S GREENFIELD AVE 90025
Certificate Information: 2122 S GREENFIELD AVE 90025
- Application / Permit
- 19016-30000-40457
- Plan Check / Job No.
- B19WL07081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel to (e) 2-story SFD. and trellis addition
- Permit Issued
- Issued on 6/12/2020
- Issuing Office
- Current Status
- CofO Issued on 4/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | KAVIAN REFAHI |
| Corrections Issued | 1/13/2020 | KAVIAN REFAHI |
| Quality Review Completed | 1/24/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 1/28/2020 | APPLICANT |
| Applicant returned to address corrections | 2/28/2020 | KAVIAN REFAHI |
| Plan Check Approved | 3/3/2020 | KAVIAN REFAHI |
| Issued | 6/12/2020 | APPLICANT |
| Building Plans Picked Up | 6/15/2020 | APPLICANT |
| CofO in Progress | 3/29/2022 | KENNETH NAGLE |
| Permit Finaled | 4/5/2022 | DANIEL ORRANTE |
| CofO Issued | 4/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/27/2020 | JOHN CONNEALLY |
| Grading Pre-Inspection | Cleared | 2/28/2020 | KAVIAN REFAHI |
| Green Code | Cleared | 3/3/2020 | RICHARD GARCIA |
Contact Information
| Architect | Hamilton,, Peter W; Lic. No.: C37714 | 1444 COLBY AVENUE #1 LOS ANGELES, CA 90025 |
| Contractor | Dixon Construction Inc; Lic. No.: 706524-B | 3169 MOUNTAIN VIEW AVE LOS ANGELES, CA 90066 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 7/22/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/3/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 8/3/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 8/27/2020 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/2/2020 | Approved | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 9/17/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 9/18/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/20/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/22/2020 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/13/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/13/2020 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/19/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/19/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 11/23/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/30/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/30/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 11/30/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 12/14/2020 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 2/16/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 2/16/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/16/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/22/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 2/22/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 2/25/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 3/2/2021 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/2/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/5/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/9/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 6/25/2021 | Approved | OGANES TARAKHCHYAN |
| Sewer | 7/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 8/9/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 9/16/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 9/16/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/16/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 9/22/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/23/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 9/24/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/24/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/24/2021 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 11/2/2021 | Partial Approval | OGANES TARAKHCHYAN |