3012 S FARMDALE AVE 90016

Certificate Information: 3012 S FARMDALE AVE 90016

Application / Permit
19016-30000-40283
Plan Check / Job No.
B19WL07041
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB494 & SB229. PER WFPP.
Permit Issued
Issued on 4/8/2020
Issuing Office
Current Status
CofO Issued on 9/27/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 JAHANSHAH POURHASSAN
Corrections Issued 12/26/2019 JAHANSHAH POURHASSAN
Plan Check Approved 3/16/2020 ALFREDO JARA
Issued 4/8/2020 APPLICANT
Building Plans Picked Up 4/15/2020 APPLICANT
CofO in Progress 7/27/2020 STUART CHAPMAN
Permit Finaled 9/27/2020 DEROLD HAUFF
CofO Issued 9/27/2020 DEROLD HAUFF
Permit Finaled 9/27/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/6/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/6/2020 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/6/2020 JEANETTE VONG
Sewer availability Cleared 2/6/2020 JEANETTE VONG
Construction near power lines Cleared 2/8/2020 RIDWAN HARDY
Flood clearance Cleared 3/12/2020 RAYMOND LAM
Hydrant and Access approval Cleared 3/13/2020 JOHN CONNEALLY

Contact Information

Contractor Gomez Construction; Lic. No.: 1049981-B 1151 S ALMA AVE      LOS ANGELES, CA 90023

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2020 Partial Approval STUART CHAPMAN
FLOOD-Elevation Certificate 5/1/2020 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 5/1/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/1/2020 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 5/6/2020 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/6/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/11/2020 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 5/11/2020 Corrections Issued STUART CHAPMAN
FLOOD-Proofing Certificate 5/11/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/11/2020 Corrections Issued STUART CHAPMAN
Insulation 5/13/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/13/2020 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 5/18/2020 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 5/18/2020 Not Ready for Inspection STUART CHAPMAN
FLOOD-Proofing Certificate 5/18/2020 Not Ready for Inspection STUART CHAPMAN
Insulation 5/18/2020 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 5/18/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/18/2020 Approved STUART CHAPMAN
Drywall Nailing 5/21/2020 Approved STUART CHAPMAN
ELECTRICAL-Rough 5/21/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/21/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/10/2020 Not Ready for Inspection STUART CHAPMAN
FLOOD-Proofing Certificate 6/10/2020 Not Ready for Inspection STUART CHAPMAN
Final 6/10/2020 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 6/10/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/12/2020 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 6/12/2020 Approved STUART CHAPMAN
Final 6/12/2020 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/12/2020 SGSOV Approved STUART CHAPMAN
Final 6/16/2020 Not Ready for Inspection STUART CHAPMAN
Final 6/18/2020 Conditional Approval STUART CHAPMAN
Final 6/29/2020 Conditional Approval STUART CHAPMAN
Service/Power Release 6/29/2020 Approved STUART CHAPMAN