13929 W VALERIO ST 91405
Certificate Information: 13929 W VALERIO ST 91405
- Application / Permit
- 19016-30000-40055
- Plan Check / Job No.
- B19WL06990
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion & addition of (e) detached garage to ADU per AB 494 & SB 229.
- Permit Issued
- Issued on 2/26/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | MANUEL GARCIA |
| Corrections Issued | 12/20/2019 | MANUEL GARCIA |
| Building Plans Picked Up | 12/20/2019 | APPLICANT |
| Plan Check Approved | 2/26/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 2/26/2020 | LADBS |
| CofO in Progress | 4/23/2024 | KIRK SANDERS |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
| CofO Issued | 5/2/2024 | RUBEN SALAS |
| Permit Finaled | 5/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2019 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2019 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 12/27/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/27/2019 | ANTHONY MAINEZ |
| Miscellaneous | Cleared | 1/28/2020 | SARAH GOLDMAN |
| Construction near power lines | Cleared | 2/20/2020 | ERNEST FRESQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 2/11/2021 | Partial Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 4/1/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/9/2021 | No Access for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 4/16/2021 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/22/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 8/12/2021 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 8/12/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/12/2021 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 8/12/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/15/2021 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Approved | WILLIAM WREN |
| HVAC-Rough | 10/29/2021 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 10/29/2021 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 11/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/6/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 1/6/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 1/6/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/6/2022 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 1/6/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/13/2022 | No Access for Inspection | KRISTEN CAUSEY |
| Insulation | 1/21/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/2/2022 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 9/1/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 9/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 10/12/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/17/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/17/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/17/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/17/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 1/30/2024 | Corrections Issued | GREGG CUMMINGS |
| Smoke Detectors | 1/30/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/15/2024 | Corrections Issued | GREGG CUMMINGS |
| Smoke Detectors | 3/15/2024 | Approved | GREGG CUMMINGS |
| Final | 4/11/2024 | Corrections Issued | KIRK SANDERS |
| Final | 4/22/2024 | OK to Issue CofO | KIRK SANDERS |