5739 W 76TH ST 90045

Certificate Information: 5739 W 76TH ST 90045

Application / Permit
19016-30000-39689
Plan Check / Job No.
B19WL06900
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detach 20'-4" X 20'-2" detached garage to an ADU including 10'-6" x 5'-8" storage and full bathroomw/ living room.per AB 494 & SB 229. all work per engineering.
Permit Issued
Issued on 2/27/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 12/19/2019 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 1/6/2020 APPLICANT
Plan Check Approved 2/3/2020 PARISA ZAHABI
Issued 2/27/2020 LADBS
CofO in Progress 7/29/2020 JUAN VALENZUELA
CofO Issued 6/15/2021 VINCENT COTTON
Permit Finaled 6/15/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 2/3/2020 ANTHONY MAINEZ
Construction near power lines Cleared 2/3/2020 TORI CHEN
Construction within easement Cleared 2/3/2020 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 2/3/2020 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 2/3/2020 ALFREDO JARA
Sewer availability Cleared 2/3/2020 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/1/2020 Partial Inspection JUAN VALENZUELA
Sewer 4/1/2020 Approved JUAN VALENZUELA
Underground Mechanical 4/1/2020 Approved JUAN VALENZUELA
Footing/Foundation/Slab 4/13/2020 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 4/15/2020 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 4/15/2020 Conditional Approval JUAN VALENZUELA
Pre-Inspection 4/30/2020 Partial Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 5/7/2020 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 5/7/2020 Corrections Issued CRAIG DAVIS
Insulation 5/7/2020 Partial Approval CRAIG DAVIS
MERV13>=Rough 5/7/2020 Partial Inspection CRAIG DAVIS
PLUMBING-Rough 5/7/2020 Corrections Issued CRAIG DAVIS
Pre-Inspection 5/14/2020 Partial Inspection ANTHONY MCDOWALL
BUILDING-Rough-Frame 5/22/2020 Approved JOHNNY MIRANDA
Insulation 5/22/2020 Approved JOHNNY MIRANDA
MERV13>=Rough 5/22/2020 Approved JOHNNY MIRANDA
Shower Pan 5/22/2020 Approved JOHNNY MIRANDA
Drywall Nailing 6/8/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 6/8/2020 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 6/23/2020 Approved JUAN VALENZUELA
Final 7/9/2020 Corrections Issued JUAN VALENZUELA
MERV13>=Final 7/9/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/9/2020 SGSOV Not Required JUAN VALENZUELA
Smoke Detectors 7/9/2020 Approved JUAN VALENZUELA
ELECTRICAL-Final 7/28/2020 Approved JUAN VALENZUELA
Final 7/28/2020 OK to Issue CofO JUAN VALENZUELA
HVAC-Final 7/28/2020 Approved JUAN VALENZUELA
PLUMBING-Final 7/28/2020 Approved JUAN VALENZUELA
Service/Power Release 7/28/2020 Approved JUAN VALENZUELA