12423 W WILSHIRE BLVD 90025
Certificate Information: 12423 W WILSHIRE BLVD 90025
- Application / Permit
- 19016-30000-39089
- Plan Check / Job No.
- B19WL06800
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- T.I. to (e) 1-story commercial bldg and change of use from medical clinic & retail to retail. No change in parking.
- Permit Issued
- Issued on 2/3/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | REZA HAGHIGHAT |
| Corrections Issued | 12/23/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 1/9/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 1/10/2020 | APPLICANT |
| Plan Check Approved | 1/30/2020 | REZA HAGHIGHAT |
| Issued | 2/3/2020 | LADBS |
| CofO in Progress | 7/20/2020 | JOHN DODGE |
| Permit Finaled | 7/21/2020 | TED RIES |
| CofO Issued | 7/21/2020 | TED RIES |
| Permit Finaled | 7/21/2020 | TED RIES |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/10/2020 | DENZEL HENDERSON |
| ZI | Cleared | 1/10/2020 | DENZEL HENDERSON |
| Supp. Use District POD/CDO/TDO | Cleared | 1/21/2020 | DYLAN SITTIG |
| ZA Case | Cleared | 1/21/2020 | DYLAN SITTIG |
| DAS Clearance | Cleared | 1/22/2020 | SOMKIAT SUPANYACHOTSKUL |
| Specific Plan | Cleared | 1/28/2020 | FREDDY GARCIA |
Contact Information
| Architect | Daham,, Ramsey Walid; Lic. No.: C34257 | 109 EUCALYPTUS DRIVE EL SEGUNDO, CA 90245 |
| Contractor | Unitrade Co; Lic. No.: 713040-B | 922 6TH STREET #7 SANTA MONICA, CA 90403 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 4/7/2020 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 4/7/2020 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 4/15/2020 | Approved | PAUL DAVIDSON |
| Insulation | 5/1/2020 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 5/1/2020 | Partial Approval | JOHN DODGE |
| Wood Frame | 5/1/2020 | Conditional Approval | JOHN DODGE |
| Drywall Nailing | 5/6/2020 | Partial Approval | JOHN DODGE |
| Insulation | 5/6/2020 | Approved | JOHN DODGE |
| Wood Frame | 5/6/2020 | Approved | JOHN DODGE |
| Drywall Nailing | 5/11/2020 | Not Ready for Inspection | JOHN DODGE |
| Drywall Nailing | 5/12/2020 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 5/13/2020 | Approved | JOHN DODGE |
| Pre-Inspection | 6/19/2020 | Approved | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Not Ready | JOHN DODGE |
| Final | 7/10/2020 | Conditional Approval | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 7/10/2020 | SGSOV No Gas | JOHN DODGE |
| Smoke Detectors | 7/10/2020 | Approved | JOHN DODGE |
| Final | 7/13/2020 | Conditional Approval | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 7/13/2020 | SGSOV No Gas | JOHN DODGE |
| Smoke Detectors | 7/13/2020 | Approved | JOHN DODGE |