1303 W 22ND PL 90007

Certificate Information: 1303 W 22ND PL 90007

Application / Permit
19016-30000-39031
Plan Check / Job No.
B19WL06783
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of existing garage, storage area and attic area to ADU per AB494 & SB229.
Permit Issued
Issued on 2/7/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 KAVIAN REFAHI
Green Plans Picked Up 1/2/2020 APPLICANT
Corrections Issued 1/15/2020 KAVIAN REFAHI
Quality Review Completed 1/15/2020 FELIX FIGUEROA
Building Plans Picked Up 1/15/2020 APPLICANT
Plan Check Approved 2/7/2020 KAVIAN REFAHI
Issued 2/7/2020 LADBS
CofO in Progress 6/15/2021 KATHRYN BUTTERWORTH
Permit Finaled 6/24/2021 DEROLD HAUFF
CofO Issued 6/24/2021 DEROLD HAUFF
Permit Finaled 6/24/2021 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 1/15/2020 SARAH GOLDMAN
Address approval Cleared 1/15/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/15/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 1/15/2020 DINAH GARIN
Sewer availability Cleared 1/15/2020 DINAH GARIN
ZI Cleared 1/15/2020 SARAH GOLDMAN
HPOZ Cleared 1/16/2020 KATIE DEBIASE
Miscellaneous Cleared 1/16/2020 KATIE DEBIASE
Miscellaneous Cleared 1/16/2020 KATIE DEBIASE
Green Code Cleared 2/3/2020 KAVIAN REFAHI

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 5919 S CROSFT AVENUE      LOS ANGELES, CA 90056
Contractor Owner-Builder       ,
Engineer Kang,, Danniel; Lic. No.: S6242 633 E 223RD ST B      CARSON, CA 90745

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/21/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 2/21/2020 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/27/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/28/2020 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/11/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/2/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 4/23/2020 Approved KATHRYN BUTTERWORTH
Shower Pan 4/23/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 4/24/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/24/2020 Approved KATHRYN BUTTERWORTH
Insulation 4/24/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Rough 4/24/2020 Approved KATHRYN BUTTERWORTH
Insulation 4/28/2020 Approved KATHRYN BUTTERWORTH
Wood Frame 4/28/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Approved KATHRYN BUTTERWORTH
Wood Frame 5/1/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 5/8/2020 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 5/12/2020 Approved SABAS ALONSO
Special/Order Compliance 5/12/2020 Corrections Issued SABAS ALONSO
Special/Order Compliance 5/19/2020 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/1/2020 Approved KATHRYN BUTTERWORTH
Final 7/1/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Final 7/1/2020 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/1/2020 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 7/1/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 7/6/2020 Corrections Issued KATHRYN BUTTERWORTH
Final 7/20/2020 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 7/20/2020 Approved KATHRYN BUTTERWORTH
Final 4/1/2021 Partial Approval KATHRYN BUTTERWORTH
Final 6/15/2021 OK to Issue CofO KATHRYN BUTTERWORTH