3750 S BOISE AVE 90066

Certificate Information: 3750 S BOISE AVE 90066

Application / Permit
19016-30000-39011
Plan Check / Job No.
B19WL06782
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) 1,423 SF SFD TO HAVE ONE (N) FULL BATH, (N) POWDER ROOM, AND REMODEL OF (E) KITCHEN & MASTER BATHROOM.
Permit Issued
Issued on 2/25/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 1/10/2022

Permit Application Status History

Green Plans Picked Up 1/6/2019 APPLICANT
Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 JAHANSHAH POURHASSAN
Corrections Issued 12/26/2019 JAHANSHAH POURHASSAN
Quality Review Completed 1/10/2020 TARIK SAOUD
Building Plans Picked Up 1/14/2020 APPLICANT
Applicant returned to address corrections 1/21/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 1/24/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 2/10/2020 JAHANSHAH POURHASSAN
Plan Check Approved 2/13/2020 JAHANSHAH POURHASSAN
Issued 2/25/2020 LADBS
Permit Finaled 1/10/2022 ENRIQUE MIRELES

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/13/2020 JAHANSHAH POURHASSAN
Green Code Cleared 2/13/2020 RICHARD GARCIA

Contact Information

Contractor T H B Construction; Lic. No.: 899602-B 4926 W 137TH STREET      HAWTHORNE, CA 90250
Engineer Tuna,, Suleyman; Lic. No.: C73294 3332 BENNETT DRIVE      LOS ANGELES, CA 90068

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/9/2020 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 4/9/2020 Corrections Issued DAVID FEILER
PLUMBING-Rough 4/9/2020 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 5/13/2020 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 5/13/2020 Corrections Issued DAVID FEILER
Gas Test 5/13/2020 Partial Inspection DAVID FEILER
HVAC-Rough 5/13/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 5/13/2020 Approved DAVID FEILER
ELECTRICAL-Rough 6/29/2020 Not Ready for Inspection DAVID HEINE
HVAC-Rough 6/29/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Rough 6/29/2020 Not Ready for Inspection DAVID HEINE
ELECTRICAL-Rough 7/2/2020 Approved JOHNNY MIRANDA
HVAC-Rough 7/2/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 7/2/2020 Approved JOHNNY MIRANDA
Wood Frame 7/2/2020 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 7/9/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 7/23/2020 Approved JOHNNY MIRANDA
Insulation 7/23/2020 Approved JOHNNY MIRANDA
Wood Frame 7/23/2020 Approved JOHNNY MIRANDA
Drywall Nailing 8/5/2020 Approved JUAN VALENZUELA
ELECTRICAL-Rough 8/5/2020 Corrections Issued JUAN VALENZUELA
Green Building Final 12/8/2020 Approved ENRIQUE MIRELES
HVAC-Final 12/8/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/8/2020 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/8/2020 Approved ENRIQUE MIRELES
Final 10/27/2021 Corrections Issued ENRIQUE MIRELES
Final 1/10/2022 Permit Finaled ENRIQUE MIRELES