200 S CONWAY AVE 90024
Certificate Information: 200 S CONWAY AVE 90024
- Application / Permit
- 19016-30000-38514
- Plan Check / Job No.
- B19WL06696
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL W/ INTERIOR & EXTERIOR ALTERATION TO (E) 2-STORY SINGLE FAMILY W/ ATT. 2-CAR GARAGE, REMOVE BEARING WALLS, ADD NEW BATHROOMS, CHANGEOUT DOORS & WINDOWS, REPLACE (E) RAILING.
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 6/16/2021
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | REZA HAGHIGHAT |
| Corrections Issued | 12/5/2019 | REZA HAGHIGHAT |
| Building Plans Picked Up | 12/9/2019 | APPLICANT |
| Plan Check Approved | 2/18/2020 | MANUEL GARCIA |
| Issued | 2/24/2020 | LADBS |
| Permit Finaled | 6/15/2021 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/29/2020 | PATRICK MISCHLICH |
Contact Information
| Architect | Williger,, Paul Brant; Lic. No.: C24022 | 26176 FAIRSIDE ROAD MALIBU, CA 90265 |
| Contractor | Santa Fe Contractors Inc; Lic. No.: 951293-B | 34385 ACTON CANYON RD ACTON, CA 93510 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 7/7/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/10/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 10/1/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 10/5/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 10/19/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 10/20/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 10/27/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 10/27/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 10/27/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 10/30/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 10/30/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 10/30/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 11/4/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 11/4/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 11/5/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 11/6/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 11/10/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/3/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/3/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 5/3/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 5/3/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/19/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/21/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 5/21/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/21/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 5/21/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/25/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 5/25/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 6/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/10/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 6/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/15/2021 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |