6237 S ACACIA ST 90056
Certificate Information: 6237 S ACACIA ST 90056
- Application / Permit
- 19016-30000-38198
- Plan Check / Job No.
- B19WL06617
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 1-STORY TYPE VB 380 SQFT GARAGE INTO ACCESSORY DWELLING UNIT, WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2019 | TARIK SAOUD |
| Corrections Issued | 11/29/2019 | TARIK SAOUD |
| Building Plans Picked Up | 12/3/2019 | APPLICANT |
| Plan Check Approved | 3/10/2020 | SERGIO SILVA |
| Issued | 3/10/2020 | LADBS |
| CofO in Progress | 12/9/2020 | JUAN VALENZUELA |
| CofO Issued | 1/11/2021 | VINCENT COTTON |
| Permit Finaled | 1/11/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 12/5/2019 | OSCAR GUTIERREZ |
| CPC | Cleared | 12/5/2019 | SARAH GOLDMAN |
| CPC | Cleared | 12/5/2019 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | OSCAR GUTIERREZ |
| Miscellaneous | Cleared | 12/5/2019 | OSCAR GUTIERREZ |
| Sewer availability | Cleared | 12/5/2019 | OSCAR GUTIERREZ |
| Construction near power lines | Cleared | 1/11/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/12/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Sewer | 3/17/2020 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 3/17/2020 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/20/2020 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/24/2020 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 4/7/2020 | Partial Inspection | JUAN VALENZUELA |
| Special/Order Compliance | 4/7/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 4/21/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 4/21/2020 | Corrections Issued | JOHNNY MIRANDA |
| Wood Frame | 4/21/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 4/28/2020 | Corrections Issued | JUAN VALENZUELA |
| Insulation | 4/28/2020 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 4/28/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/3/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/3/2020 | Corrections Issued | JUAN VALENZUELA |
| Gas Test | 6/3/2020 | Partial Approval | JUAN VALENZUELA |
| Insulation | 6/3/2020 | Partial Inspection | JUAN VALENZUELA |
| METHANE-Rough | 6/3/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 6/3/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/9/2020 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/9/2020 | Approved | JUAN VALENZUELA |
| Insulation | 6/9/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 6/9/2020 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/6/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/6/2020 | Approved | JUAN VALENZUELA |
| Final | 10/28/2020 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 10/28/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 10/28/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/9/2020 | Approved | JUAN VALENZUELA |
| Final | 12/9/2020 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 12/9/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 12/9/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Approved | JUAN VALENZUELA |