7240 N FULTON AVE 91605

Certificate Information: 7240 N FULTON AVE 91605

Application / Permit
19016-30000-36415
Plan Check / Job No.
B19WL06323
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) Music School or Studio
Work Description
change of use and TI portion of existing light manufacturing/storage building to music studio/school.
Permit Issued
Issued on 1/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 11/25/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 12/4/2019 FELIX FIGUEROA
Disabled Access Plans Picked Up 12/6/2019 APPLICANT
Plan Check Approved 1/15/2020 KAMRAN GHOTBI RAVANDI
Issued 1/16/2020 LADBS
Building Plans Picked Up 5/11/2020 APPLICANT
TCO Issued (Expire Date: 08-25-2021) 2/26/2021 RICKEY JACKSON
TCO Issued (Expire Date: 02-28-2022) 9/1/2021 JEFFREY DURAN
CofO in Progress 5/13/2022 ANDREW DORSO
CofO Issued 6/7/2022 JEFFREY DURAN
Permit Finaled 6/7/2022 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/6/2020 GUILLERMO PETRA
Sewer availability Cleared 1/6/2020 GUILLERMO PETRA
DAS Clearance Cleared 1/7/2020 SOMKIAT SUPANYACHOTSKUL

Contact Information

Contractor Wright J P Construction Inc; Lic. No.: 844971-B 557 IVY STREET      GLENDALE, CA 91204

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/21/2020 Partial Inspection ROBERT DAVIS
Deputy Drilled-In Anchors 4/6/2020 Conditional Approval ANDREW DORSO
Wood Frame 4/17/2020 Partial Inspection DAVID BURKHEAD
Drywall Nailing 4/22/2020 Partial Inspection ANDREW DORSO
Drywall Nailing 5/15/2020 Corrections Issued ANDREW DORSO
Drywall Nailing 5/18/2020 Partial Inspection ANDREW DORSO
Special/Order Compliance 5/18/2020 Approved ANDREW DORSO
Insulation 6/15/2020 Partial Inspection ANDREW DORSO
Wood Frame 6/15/2020 Approved ANDREW DORSO
Insulation 6/17/2020 Approved ANDREW DORSO
Drywall Nailing 6/23/2020 Partial Inspection ANDREW DORSO
Drywall Nailing 6/30/2020 Approved ANDREW DORSO
Final 10/7/2020 Not Ready for Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 10/7/2020 SGSOV Not Ready ANDREW DORSO
Smoke Detectors 10/7/2020 Approved ANDREW DORSO
Final 10/14/2020 Not Ready for Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Not Ready ANDREW DORSO
Final 2/18/2021 Corrections Issued ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Approved ANDREW DORSO
Special/Order Compliance 7/28/2021 Partial Inspection ANDREW DORSO
Special/Order Compliance 8/18/2021 No Access for Inspection ANDREW DORSO
Special/Order Compliance 2/2/2022 Partial Inspection ANDREW DORSO
Final 5/13/2022 OK to Issue CofO ANDREW DORSO