2873 S MOTOR AVE 90064
Certificate Information: 2873 S MOTOR AVE 90064
- Application / Permit
- 19016-30000-36095
- Plan Check / Job No.
- B19WL06260
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior & exterior alteration to (e) SFD with door and windows changeout and add a new cantilevered balcony at rear side.
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/30/2023
Permit Application Status History
| Submitted | 11/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | ALFREDO JARA |
| Corrections Issued | 11/15/2019 | ALFREDO JARA |
| Building Plans Picked Up | 11/20/2019 | APPLICANT |
| Plan Check Approved | 12/5/2019 | REZA HAGHIGHAT |
| Issued | 4/26/2021 | APPLICANT |
| Permit Finaled | 3/28/2023 | ASHLEY THOMPSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2019 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 11/25/2019 | AL GAMBLE |
| Roof/Waste drainage to street | Cleared | 11/25/2019 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Alisal Builders Corp; Lic. No.: 732777-B | P O BOX 6038 SAN PEDRO, CA 90734 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/29/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 7/12/2021 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 9/13/2021 | Conditional Approval | KEVIN SARGSYAN |
| HVAC-Rough | 10/27/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/27/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/8/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/12/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/12/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/17/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/17/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/17/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 11/29/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 1/11/2022 | No Access for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 1/13/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 1/21/2022 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/28/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 2/1/2022 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 2/2/2022 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 2/25/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 3/2/2022 | Approved | KEVIN SARGSYAN |
| Insulation | 3/2/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 3/4/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 3/16/2022 | Approved | KEVIN SARGSYAN |
| Shower Pan | 3/16/2022 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/2/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 2/21/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 2/21/2023 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Final | 2/28/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 2/28/2023 | Corrections Issued | MICHAEL PELHAM |
| Gas Test | 2/28/2023 | Approved | MICHAEL PELHAM |
| HVAC-Final | 2/28/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Final | 2/28/2023 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | MICHAEL PELHAM |
| Smoke Detectors | 2/28/2023 | Approved | MICHAEL PELHAM |
| Final | 3/2/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 3/2/2023 | SGSOV Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 3/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 3/16/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 3/22/2023 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 3/22/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 3/22/2023 | Approved | ASHLEY THOMPSON |
| Final | 3/23/2023 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 3/23/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 3/28/2023 | Permit Finaled | ASHLEY THOMPSON |