- Work Description
- Decrease portion of warehouse to increase office. Demolition of (e) mezzanine, two new mezzanine connected with a bridge new ground level tenant improvement.
- Permit Issued
- Issued on 3/4/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/5/2023
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | MANUEL GARCIA |
| Corrections Issued | 12/4/2019 | MANUEL GARCIA |
| Quality Review Completed | 12/11/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 12/11/2019 | APPLICANT |
| Building Plans Picked Up | 12/12/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 12/12/2019 | APPLICANT |
| Applicant returned to address corrections | 1/17/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 1/29/2020 | MANUEL GARCIA |
| Plan Check Approved | 2/18/2020 | MANUEL GARCIA |
| Issued | 3/4/2020 | LADBS |
| Permit Finaled | 5/2/2023 | ALAN MORELOS |
Permit Application Clearance Information
| Prkng lot landscape/Water mgmt | Cleared | 1/29/2020 | DENZEL HENDERSON |
| ZI | Cleared | 2/5/2020 | GISELLE CORELLA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/10/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 2/11/2020 | RICHARD GARCIA |
| Community Plan Implem. Overlay | Cleared | 2/12/2020 | HELEN JADALI |
| DAS Clearance | Cleared | 2/12/2020 | SOMKIAT SUPANYACHOTSKUL |
Contact Information
| Architect | 4023, Moore St; Lic. No.: C34605 | LOS ANGELES, CA, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Greco,, Adam Matthew; Lic. No.: S4077 | 1470 WESTERLY TERRACE LOS ANGELES, CA 90026 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/12/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 6/12/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 6/19/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 6/25/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Reinf. Concrete | 7/1/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 7/14/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 7/14/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Structural Steel Frame | 7/14/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Wood Frame | 7/21/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 7/23/2020 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 7/28/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Shotcrete | 7/28/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Reinforced Concrete Frame | 7/28/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 9/16/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 9/17/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 1/13/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Wood Frame | 1/13/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 2/10/2021 | Approved | LANNY MERRICK |
| Insulation | 2/10/2021 | Approved | LANNY MERRICK |
| Wood Frame | 2/10/2021 | Approved | LANNY MERRICK |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2021 | Conditional Approval | LANNY MERRICK |
| Insulation | 3/24/2021 | Approved | LANNY MERRICK |
| Drywall Nailing | 4/7/2021 | Approved | DANIEL COLLINS |
| Drywall Nailing | 7/14/2021 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 7/14/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Light Gage Steel Frame | 7/14/2021 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 7/28/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Final | 12/19/2022 | Not Ready for Inspection | ALAN MORELOS |
| Green Building Final | 12/19/2022 | Not Ready for Inspection | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Not Ready | ALAN MORELOS |
| Smoke Detectors | 12/19/2022 | Not Ready for Inspection | ALAN MORELOS |
| Final | 5/2/2023 | Permit Finaled | ALAN MORELOS |
| Green Building Final | 5/2/2023 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 5/2/2023 | Approved | ALAN MORELOS |