2954 S VETERAN AVE 90064
Certificate Information: 2954 S VETERAN AVE 90064
- Application / Permit
- 19016-30000-35252
- Plan Check / Job No.
- B19WL06135
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing sun room at rear of dwelling to bedroom with restroom addition.
- Permit Issued
- Issued on 4/28/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 11/1/2019 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 4/23/2020 | PARISA ZAHABI |
| Issued | 4/28/2020 | LADBS |
| Building Plans Picked Up | 4/28/2020 | APPLICANT |
| Permit Finaled | 4/3/2025 | RICHARD STEINBACH |
| CofO Issued | 4/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2019 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/1/2019 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 11/4/2019 | AL GAMBLE |
| Roof/Waste drainage to street | Cleared | 4/16/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/12/2020 | Approved | KENNETH NAGLE |
| Deputy Drilled-In Anchors | 5/13/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/21/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 5/21/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 5/28/2020 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/11/2020 | Approved | JUSTIN CURTIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Partial Approval | JUSTIN CURTIS |
| PLUMBING-Rough | 6/11/2020 | Approved | JUSTIN CURTIS |
| HVAC-Rough | 6/15/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Wood Frame | 6/15/2020 | Approved | JUSTIN CURTIS |
| Insulation | 6/17/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/17/2020 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 6/19/2020 | Approved | JUSTIN CURTIS |
| Service/Power Release | 6/26/2020 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/14/2020 | Approved | EVAN COOPER |
| Final | 8/14/2020 | Conditional Approval | EVAN COOPER |
| Green Building Final | 8/14/2020 | Approved | EVAN COOPER |
| Green Building Rough | 8/14/2020 | Approved | EVAN COOPER |
| MERV13>=Final | 8/14/2020 | Approved | EVAN COOPER |
| MERV13>=Rough | 8/14/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/14/2020 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/14/2020 | Approved | EVAN COOPER |