1207-1209 S MALGREN AVE 90732
Certificate Information: 1207-1209 S MALGREN AVE 90732
- Application / Permit
- 19016-30000-34659
- Plan Check / Job No.
- B19WL06031
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHCED GARAGE INTO AN ADU PER AB 494 & SB229.
- Permit Issued
- Issued on 12/3/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | REZA HAGHIGHAT |
| Corrections Issued | 11/1/2019 | REZA HAGHIGHAT |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Plan Check Approved | 12/3/2019 | JAHANSHAH POURHASSAN |
| Issued | 12/3/2019 | LADBS |
| CofO in Progress | 8/6/2020 | JOHN KLARIN |
| No Progress | 8/10/2020 | WILLIAM ROSE |
| CofO in Progress | 8/10/2020 | WILLIAM ROSE |
| CofO in Progress | 8/24/2020 | WILLIAM ROSE |
| No Progress | 8/24/2020 | ANSON MAGLASANG |
| CofO in Progress | 8/24/2020 | ANSON MAGLASANG |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
| CofO Issued | 9/3/2020 | DEROLD HAUFF |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2019 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2019 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 11/15/2019 | NIKTA MOUSAVI |
| Construction near power lines | Cleared | 11/25/2019 | OSCAR CASTRO |
Contact Information
| Contractor | Foundation To Roof Inc; Lic. No.: 767761-B | 10800 SOUTH LA CIENEGA BL INGLEWOOD, CA 90304 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/24/2019 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 1/10/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 1/10/2020 | Partial Inspection | JOHN KLARIN |
| Underground Mechanical | 1/10/2020 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 1/17/2020 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 1/23/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 1/23/2020 | Conditional Approval | ANSON MAGLASANG |
| Underground Mechanical | 1/23/2020 | Corrections Issued | ANSON MAGLASANG |
| Underground Mechanical | 2/6/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| Wood Frame | 2/6/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/21/2020 | Approved | ANSON MAGLASANG |
| Sewer | 2/21/2020 | Approved | ANSON MAGLASANG |
| Underground Mechanical | 2/21/2020 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Rough | 3/25/2020 | Approved | JOHN KLARIN |
| Wood Frame | 3/25/2020 | Partial Approval | JOHN KLARIN |
| PLUMBING-Rough | 3/31/2020 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 4/17/2020 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 4/22/2020 | Approved | JOHN KLARIN |
| Insulation | 4/22/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 4/24/2020 | Corrections Issued | JOHN KLARIN |
| Insulation | 4/24/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 4/29/2020 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 4/29/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 4/29/2020 | Partial Approval | BRIAN CHRISTIAN |
| Shower Pan | 5/6/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 5/12/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 7/2/2020 | Approved | JOHN KLARIN |
| Final | 7/2/2020 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 7/2/2020 | Approved | JOHN KLARIN |
| PLUMBING-Final | 7/2/2020 | Approved | JOHN KLARIN |
| Service/Power Release | 7/2/2020 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/17/2020 | Approved | JOHN KLARIN |
| Final | 7/17/2020 | Corrections Issued | JOHN KLARIN |
| Gas Test | 7/17/2020 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/17/2020 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 7/17/2020 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 7/17/2020 | Approved | JOHN KLARIN |
| Final | 8/5/2020 | Conditional Approval | JOHN KLARIN |
| Service/Power Release | 8/5/2020 | Approved | JOHN KLARIN |