12530 W BARBARA AVE 90066

Certificate Information: 12530 W BARBARA AVE 90066

Application / Permit
19016-30000-33659
Plan Check / Job No.
B19WL05879
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (e) SFD and (n) first floor addition
Permit Issued
Issued on 11/22/2022
Issuing Office
Current Status
Issued on 11/22/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/21/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 ALFREDO JARA
Corrections Issued 10/25/2019 ALFREDO JARA
Applicant returned to address corrections 11/19/2019 JAHANSHAH POURHASSAN
Plan Check Approved 11/20/2019 KAVIAN REFAHI
No Progress 11/11/2021 KAVIAN REFAHI
Plan Check Approved 12/17/2021 JASON JANGADA
Issued 11/22/2022 APPLICANT
Building Plans Picked Up 12/13/2022 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 11/29/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/30/2021 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 12/1/2021 STEVEN JIN

Contact Information

Contractor Williamson John Construction Inc; Lic. No.: 451421-B 8723 BLERIOT AVE      LOS ANGELES, CA 90045
Engineer Yu,, Irene Gailen; Lic. No.: C68382 3411 CAROLINE AVE      CULVER CITY, CA 90232

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/25/2023 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/2/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 2/2/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 3/9/2023 Conditional Approval JESUS RODRIGUEZ
Reinforced Masonry Frame 3/9/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 3/31/2023 Approved JESUS RODRIGUEZ
Deputy Wood Construction 4/6/2023 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 4/6/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Approved JESUS PINEDA
Shower Pan 4/10/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/5/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 5/5/2023 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Rough 5/5/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 5/5/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 5/5/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 5/23/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 5/23/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 6/5/2023 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 6/7/2023 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 6/7/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/7/2023 Approved JESUS RODRIGUEZ
Final 6/23/2023 Corrections Issued JESUS RODRIGUEZ
Insulation 6/23/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 7/6/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/6/2023 Approved JESUS RODRIGUEZ
Green Building Rough 7/6/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/3/2024 Corrections Issued JESUS PINEDA
Gas Test 9/13/2024 Corrections Issued JESUS PINEDA
PLUMBING-Final 9/13/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved JESUS PINEDA
Gas Test 9/16/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Approved JESUS PINEDA
ELECTRICAL-Final 2/19/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Final 3/17/2025 Approved MICHAEL ALLEN
Service/Power Release 3/17/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/2/2026 Corrections Issued DAVID FEILER