700 E JACKSON ST 90012
Certificate Information: 700 E JACKSON ST 90012
- Application / Permit
- 19016-30000-33518
- Plan Check / Job No.
- B19WL05855
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- (N) grain silo foundation pad and anchorage
- Permit Issued
- Issued on 5/22/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 7/31/2023
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/24/2019 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Plan Check Approved | 12/21/2022 | KHUONG TRUONG |
| Issued | 5/22/2023 | APPLICANT |
| Permit Finaled | 7/31/2023 | JULIAN CAPUCETTI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | M C Concrete; Lic. No.: 1051344-C-8 | 40853 25TH ST W PALMDALE, CA 93551 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 5/30/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Approved | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 6/7/2023 | Approved | JULIAN CAPUCETTI |
| Final | 7/31/2023 | Permit Finaled | JULIAN CAPUCETTI |
| Smoke Detectors | 7/31/2023 | Approved | JULIAN CAPUCETTI |